桥梁混凝土结构防腐施工方案

目 录

1工程概况 ······························································································· 1

1.1 工程情况 ····················································································· 1

1.2 工程环境 ····················································································· 1

1.3 结构防腐施工内容 ····································································· 1

1.4 防腐材料的选用 ········································································· 2 2防腐施工控制目标 ··············································································· 2 3混凝土结构防腐施工方案 ··································································· 3

3.1防腐材料底层、面层的施工方案 ············································· 3

3.2 UGD-3510憎水性混凝土保护剂的施工方案 ··························· 5 4 质量保证措施 ······················································································ 6 5 安全保证措施 ······················································································ 8 6 文明施工措施 ······················································································ 8

桥梁混凝土结构防腐施工方案

1工程概况

1.1 工程情况

海滨大道南段二期工程第三合同段,设计范围为K22+600~K29+914.671,主要构筑物有红旗路互通式立交以及子牙新河特大桥1。红旗路互通式立下部结构除A7号墩为沿主线方向布置单排桩接承台外,其余均为双排桩接承台基础形式。子牙新河特大桥1为钻孔灌注桩接承台(或系梁)接墩柱形式。

1.2 工程环境

本工程地处天津渤海之滨,属于滨海盐碱土和盐碱水环境,其地质多为海相沉积形成,富含CL-、SO42-等多种离子。根据地质勘察报告,红旗路立交桥

和子牙新河特大桥结构所处环境类型为Ⅱ类,地下水对混凝土存在结晶类腐蚀,腐蚀等级为严重腐蚀,对钢筋混凝土存在结晶分解复核类腐蚀,腐蚀等级为严重腐蚀,其中渤海湾海滩及紧邻渤海湾主河槽及盐田范围,地下水有严重腐蚀性,采用特殊防腐设计。综合以上因素,确定本工程环境类别为Ⅳ类。

1.3 结构防腐施工内容

根据设计要求,本工程混凝土结构防腐施工包括:

1墩柱标高5.0m以下(原地面标高高于5.0m的墩柱,以地面以上0.5m○

为准)外表面涂刷防腐涂料(底层丙烯酸树脂封闭漆+面层丙烯酸树脂漆)厚度250µm。

2墩柱标高5.0m以上(原地面标高高于5.0m的墩柱,以地面以上0.5m○

为准)桥梁工程全部完工后暴露在空气中的所有混凝土结构(包括盖梁、支

座垫石、挡块、中横梁、端横梁、跨中横梁、防撞护栏等外露面)表面进行硅烷浸渍处理,厚度250µm。

1.4 防腐材料的选用

根据设计要求,我单位在墩柱标高5.0m以下表面,分底层和面层分两层涂刷防腐涂料,底层选用UGD-3610混凝土防锈封闭底漆,它是一种高效环保的混凝土界面封闭产品,可作为混凝土结构封闭剂,加强基层的致密性。

面层选用UGD-3710 LOG丙烯酸树脂混凝土高弹保护涂料,其主要作用是可以抵御盐类及其他各类化学物质和气候变化的侵蚀,防止碳化反应的发生和发展。

墩柱标高5.0m以上混凝土外露表面均采用硅烷产品,UGD-3510憎水性混凝土保护剂,其含有有机硅烷和锈蚀抑制剂,渗透能力强,可以保护混凝土不受酸、碱、各类油脂和盐类等的侵蚀。

2防腐施工控制目标

根据《建筑防腐蚀工程施工及验收规范》(GB50212-2002)及《建筑防腐蚀工程质量检验评定标准》(GB50224-95),混凝土结构防腐施工应满足以下目标要求:

1、所用材料必须经过检验合格,并按照相关规定对有关材料进行复检,施工配合比经过监理站审核合格后方可使用。

2、施工过程中严格按照设计要求和相关规定施工,材料用量严格按照施工配合比使用,施工质量符合相关验收标准。

3、各个工序施工要注意成品保护,上道工序完成后,下道工序施工确保对上道工序的成品无损坏、污染。

4、保证涂层与混凝土表面的粘结力不小于1.5MPa。

5、各个涂层要涂刷到位,不得漏刷。

3混凝土结构防腐施工方案

3.1防腐材料底层、面层的施工方案

其施工工艺流程为:施工准备→基面清理→涂刷底层UGD-3610混凝土防锈封闭底漆→涂刷面层UGD-3710 LOG丙烯酸树脂混凝土高弹保护涂料→清理现场。其施工工艺框图见下页图 图1 底层、面层涂料施工工艺框图。

1施工准备 现场按照安全施工措施搭设脚手架,安装吊篮,经安全检查○

合格后方可进行防腐材料涂刷工作。

2基面处理 清除混凝土表面钢筋头,清理表面油渍、淤泥、浮浆,凿去○

表面胀裂或松动的混凝土。用电动角磨机打磨混凝土表面,用高压水枪喷射冲洗混凝土表面,冲洗后自然干燥。 要求冲洗后混凝土表面应洁净、牢固密实无松动,对混凝土局部大的凹陷、孔洞及裂缝处可以采用丙烯酸乳胶水泥砂浆进行局部修补,再用丙烯酸乳胶水泥腻子批刮,也可以先涂装环氧封闭底漆,然后用环氧腻子批刮补平。

3底层防腐涂料涂刷 基面清理经过报检验收合格后即进行底层涂料的○

涂刷施工,施工采用喷枪、滚筒、刷子喷涂或涂刷UGD-3610混凝土防锈封闭底漆,施工现场配备计量设备,严格按照配合比添加各种材料用量,为使涂料涂刷均匀、密实,施工分两遍涂刷,待第一遍膜表干后再施工第二遍。

4面层防腐涂料涂刷 待底层防腐涂料风干后清理底层表面灰尘等,检查○

是否有漏刷等现象,经过报检合格后即进行面层UGD-3710 LOG丙烯酸树脂混凝土高弹保护涂料的施工,所用材料要严格按照配合比要求施配,并认真搅拌均匀,注意不能添加任何诸如水等稀释剂,涂刷时应始终沿同一方向进行,

为使涂料表面均匀、密实,施工分两遍涂刷,第一遍涂层表干后涂刷第二遍,涂刷方向与第一遍垂直,要求涂刷完成涂膜干燥后,混凝土表面密实,有可见漆层。

5现场清理 施工完毕后,清理施工现场,将剩余材料按照相关规定处理,○

以免造成环境污染。

3.2 UGD-3510憎水性混凝土保护剂的施工方案

其施工工艺流程为:施工准备→基面处理→涂刷UGD-3510憎水性混凝土保护剂→清理现场。其施工工艺框图见下图 图2 UGD-3510涂料施工工艺框图。

1施工准备 现场按照安全施工措施搭设脚手架,安装吊篮,经安全检查○

合格后方可进行防腐材料涂刷工作。

2基面处理 清除混凝土表面钢筋头,清洗表面油渍、淤泥、浮浆,凿去○

表面胀裂或松动的混凝土。用电动角磨机打磨混凝土表面,用高压水枪喷射冲洗混凝土表面,冲洗后自然干燥。 要求冲洗后混凝土表面应洁净、牢固密实无松动,对混凝土局部大的凹陷、孔洞可以采用砂浆修补平整。

3 UGD-3510憎水性混凝土保护剂涂刷 基面清理经过报检验收合格后即○

进行防腐涂料的涂刷施工,施工采用喷枪、滚筒、刷子喷涂或涂刷,一般情况,每个部位涂刷一遍即可,如结构表面过于疏松可施工两遍。

4现场清理 施工完毕后,清理施工现场,将剩余材料按照相关规定处理,○

以免造成环境污染。

涂刷后,涂料经过自然养护即可。

4 质量保证措施

1、建立健全质量保证体系、质量管理和质量自检组织机构

(1)质量保证体系

本工程质量管理保证体系的建立原则为:紧紧围绕投标承诺的质量创优目标,制订切实可行的质量创优规划,坚持“以人为本”的观点,通过政治思想工作,相应的组织保证措施和及时准确的质量管理信息系统,实现项目施工整个过程的质量控制。

(2)质量管理组织机构

质量管理组织机构由项目经理牵头,由项目总工程师、项目质检负责人、项目经理部各部门负责人、各工程队队长及质检员、项目经理部的有关业务

人员参加组成质量管理领导小组。形成内外贯通、纵横到位的质量管理组织体系。

质量自检组织机构由项目经理部质检负责人和技术部、试验室负责人组成。质检负责人全面负责质量检查和监督工作,在质量把关方面直接对法人代表负责,在质量管理方面有一票否决权。

2、加强施工技术指导,加大监控力度

配足各专业工程师、技术员与测试、质检人员,定岗定责。施工前进行切实可行的技术交底。严格按设计图、相关的技术规范及操作规程要求进行施工。技术人员深入现场精心指导,测试与质检人员准确检测,严格把关。强化工序、工程、工艺质量控制。

3、落实各项规章制度

结合本工序实际,组织全体施工人员学习相关设计图纸、施工规范及操作规程,使全员明确标准,全方位有章可循,全过程措施到位。严格执行优质优价制、安全质量事故处罚制、质量否决制等规定。落实设计变更、质量验评程序与奖罚,以及工序自检、互检、交接检的“三检制”,与工班初检、工程队复检、项目部终检的“三检制”等制度。

4、严格把好材料的质量关

严格执行设计以及有关规范要求,全部材料均应有质保书。进场时,必须提供出厂合格证或产品技术鉴定书,严格进行材质、规格及外观检验,并按规定进行复试检验,经监理工程师确认达标后方可使用,杜绝使用假冒伪劣产品。

5 安全保证措施

1开工前召开安全专题会议,对施工人员进行安全教育培训,宣传安全生○

产的重要性,提高工人的安全意识。

2现场施工多为高空作业,○严格按照高空作业施工方案以及脚手架施工方案进行设施搭设,并按照相关要求采取安全防护措施。

3现场设置专职安全员,全面负责现场安全检查、监督工作,施工中要全○

天巡查,发现安全隐患立即停工整改,待排查隐患后再进行施工。

4材料进场要集中存放,对于易燃物品要有专人负责看管,并堆放场地要○

备有消防设备。

5高空人员每人配备安全绳和安全带各一套,○各种施工机具要与安全绳连接,防止坠落。

6雨雪天气不得施工。 ○

6 文明施工措施

1、进入施工现场人员严格遵守各种规章制度,不得打架斗殴。 ○

2、现场材料按照种类堆放整齐,不得乱放。 ○

3、施工作业面做到工完料尽,对于剩余的工程材料、废料分类存放到指○

定地点,每天完工后对作业面进行清理。

4、○生活区域和施工现场不得乱扔垃圾,尤其废料,不得对环境造成污染。

目 录

1工程概况 ······························································································· 1

1.1 工程情况 ····················································································· 1

1.2 工程环境 ····················································································· 1

1.3 结构防腐施工内容 ····································································· 1

1.4 防腐材料的选用 ········································································· 2 2防腐施工控制目标 ··············································································· 2 3混凝土结构防腐施工方案 ··································································· 3

3.1防腐材料底层、面层的施工方案 ············································· 3

3.2 UGD-3510憎水性混凝土保护剂的施工方案 ··························· 5 4 质量保证措施 ······················································································ 6 5 安全保证措施 ······················································································ 8 6 文明施工措施 ······················································································ 8

桥梁混凝土结构防腐施工方案

1工程概况

1.1 工程情况

海滨大道南段二期工程第三合同段,设计范围为K22+600~K29+914.671,主要构筑物有红旗路互通式立交以及子牙新河特大桥1。红旗路互通式立下部结构除A7号墩为沿主线方向布置单排桩接承台外,其余均为双排桩接承台基础形式。子牙新河特大桥1为钻孔灌注桩接承台(或系梁)接墩柱形式。

1.2 工程环境

本工程地处天津渤海之滨,属于滨海盐碱土和盐碱水环境,其地质多为海相沉积形成,富含CL-、SO42-等多种离子。根据地质勘察报告,红旗路立交桥

和子牙新河特大桥结构所处环境类型为Ⅱ类,地下水对混凝土存在结晶类腐蚀,腐蚀等级为严重腐蚀,对钢筋混凝土存在结晶分解复核类腐蚀,腐蚀等级为严重腐蚀,其中渤海湾海滩及紧邻渤海湾主河槽及盐田范围,地下水有严重腐蚀性,采用特殊防腐设计。综合以上因素,确定本工程环境类别为Ⅳ类。

1.3 结构防腐施工内容

根据设计要求,本工程混凝土结构防腐施工包括:

1墩柱标高5.0m以下(原地面标高高于5.0m的墩柱,以地面以上0.5m○

为准)外表面涂刷防腐涂料(底层丙烯酸树脂封闭漆+面层丙烯酸树脂漆)厚度250µm。

2墩柱标高5.0m以上(原地面标高高于5.0m的墩柱,以地面以上0.5m○

为准)桥梁工程全部完工后暴露在空气中的所有混凝土结构(包括盖梁、支

座垫石、挡块、中横梁、端横梁、跨中横梁、防撞护栏等外露面)表面进行硅烷浸渍处理,厚度250µm。

1.4 防腐材料的选用

根据设计要求,我单位在墩柱标高5.0m以下表面,分底层和面层分两层涂刷防腐涂料,底层选用UGD-3610混凝土防锈封闭底漆,它是一种高效环保的混凝土界面封闭产品,可作为混凝土结构封闭剂,加强基层的致密性。

面层选用UGD-3710 LOG丙烯酸树脂混凝土高弹保护涂料,其主要作用是可以抵御盐类及其他各类化学物质和气候变化的侵蚀,防止碳化反应的发生和发展。

墩柱标高5.0m以上混凝土外露表面均采用硅烷产品,UGD-3510憎水性混凝土保护剂,其含有有机硅烷和锈蚀抑制剂,渗透能力强,可以保护混凝土不受酸、碱、各类油脂和盐类等的侵蚀。

2防腐施工控制目标

根据《建筑防腐蚀工程施工及验收规范》(GB50212-2002)及《建筑防腐蚀工程质量检验评定标准》(GB50224-95),混凝土结构防腐施工应满足以下目标要求:

1、所用材料必须经过检验合格,并按照相关规定对有关材料进行复检,施工配合比经过监理站审核合格后方可使用。

2、施工过程中严格按照设计要求和相关规定施工,材料用量严格按照施工配合比使用,施工质量符合相关验收标准。

3、各个工序施工要注意成品保护,上道工序完成后,下道工序施工确保对上道工序的成品无损坏、污染。

4、保证涂层与混凝土表面的粘结力不小于1.5MPa。

5、各个涂层要涂刷到位,不得漏刷。

3混凝土结构防腐施工方案

3.1防腐材料底层、面层的施工方案

其施工工艺流程为:施工准备→基面清理→涂刷底层UGD-3610混凝土防锈封闭底漆→涂刷面层UGD-3710 LOG丙烯酸树脂混凝土高弹保护涂料→清理现场。其施工工艺框图见下页图 图1 底层、面层涂料施工工艺框图。

1施工准备 现场按照安全施工措施搭设脚手架,安装吊篮,经安全检查○

合格后方可进行防腐材料涂刷工作。

2基面处理 清除混凝土表面钢筋头,清理表面油渍、淤泥、浮浆,凿去○

表面胀裂或松动的混凝土。用电动角磨机打磨混凝土表面,用高压水枪喷射冲洗混凝土表面,冲洗后自然干燥。 要求冲洗后混凝土表面应洁净、牢固密实无松动,对混凝土局部大的凹陷、孔洞及裂缝处可以采用丙烯酸乳胶水泥砂浆进行局部修补,再用丙烯酸乳胶水泥腻子批刮,也可以先涂装环氧封闭底漆,然后用环氧腻子批刮补平。

3底层防腐涂料涂刷 基面清理经过报检验收合格后即进行底层涂料的○

涂刷施工,施工采用喷枪、滚筒、刷子喷涂或涂刷UGD-3610混凝土防锈封闭底漆,施工现场配备计量设备,严格按照配合比添加各种材料用量,为使涂料涂刷均匀、密实,施工分两遍涂刷,待第一遍膜表干后再施工第二遍。

4面层防腐涂料涂刷 待底层防腐涂料风干后清理底层表面灰尘等,检查○

是否有漏刷等现象,经过报检合格后即进行面层UGD-3710 LOG丙烯酸树脂混凝土高弹保护涂料的施工,所用材料要严格按照配合比要求施配,并认真搅拌均匀,注意不能添加任何诸如水等稀释剂,涂刷时应始终沿同一方向进行,

为使涂料表面均匀、密实,施工分两遍涂刷,第一遍涂层表干后涂刷第二遍,涂刷方向与第一遍垂直,要求涂刷完成涂膜干燥后,混凝土表面密实,有可见漆层。

5现场清理 施工完毕后,清理施工现场,将剩余材料按照相关规定处理,○

以免造成环境污染。

3.2 UGD-3510憎水性混凝土保护剂的施工方案

其施工工艺流程为:施工准备→基面处理→涂刷UGD-3510憎水性混凝土保护剂→清理现场。其施工工艺框图见下图 图2 UGD-3510涂料施工工艺框图。

1施工准备 现场按照安全施工措施搭设脚手架,安装吊篮,经安全检查○

合格后方可进行防腐材料涂刷工作。

2基面处理 清除混凝土表面钢筋头,清洗表面油渍、淤泥、浮浆,凿去○

表面胀裂或松动的混凝土。用电动角磨机打磨混凝土表面,用高压水枪喷射冲洗混凝土表面,冲洗后自然干燥。 要求冲洗后混凝土表面应洁净、牢固密实无松动,对混凝土局部大的凹陷、孔洞可以采用砂浆修补平整。

3 UGD-3510憎水性混凝土保护剂涂刷 基面清理经过报检验收合格后即○

进行防腐涂料的涂刷施工,施工采用喷枪、滚筒、刷子喷涂或涂刷,一般情况,每个部位涂刷一遍即可,如结构表面过于疏松可施工两遍。

4现场清理 施工完毕后,清理施工现场,将剩余材料按照相关规定处理,○

以免造成环境污染。

涂刷后,涂料经过自然养护即可。

4 质量保证措施

1、建立健全质量保证体系、质量管理和质量自检组织机构

(1)质量保证体系

本工程质量管理保证体系的建立原则为:紧紧围绕投标承诺的质量创优目标,制订切实可行的质量创优规划,坚持“以人为本”的观点,通过政治思想工作,相应的组织保证措施和及时准确的质量管理信息系统,实现项目施工整个过程的质量控制。

(2)质量管理组织机构

质量管理组织机构由项目经理牵头,由项目总工程师、项目质检负责人、项目经理部各部门负责人、各工程队队长及质检员、项目经理部的有关业务

人员参加组成质量管理领导小组。形成内外贯通、纵横到位的质量管理组织体系。

质量自检组织机构由项目经理部质检负责人和技术部、试验室负责人组成。质检负责人全面负责质量检查和监督工作,在质量把关方面直接对法人代表负责,在质量管理方面有一票否决权。

2、加强施工技术指导,加大监控力度

配足各专业工程师、技术员与测试、质检人员,定岗定责。施工前进行切实可行的技术交底。严格按设计图、相关的技术规范及操作规程要求进行施工。技术人员深入现场精心指导,测试与质检人员准确检测,严格把关。强化工序、工程、工艺质量控制。

3、落实各项规章制度

结合本工序实际,组织全体施工人员学习相关设计图纸、施工规范及操作规程,使全员明确标准,全方位有章可循,全过程措施到位。严格执行优质优价制、安全质量事故处罚制、质量否决制等规定。落实设计变更、质量验评程序与奖罚,以及工序自检、互检、交接检的“三检制”,与工班初检、工程队复检、项目部终检的“三检制”等制度。

4、严格把好材料的质量关

严格执行设计以及有关规范要求,全部材料均应有质保书。进场时,必须提供出厂合格证或产品技术鉴定书,严格进行材质、规格及外观检验,并按规定进行复试检验,经监理工程师确认达标后方可使用,杜绝使用假冒伪劣产品。

5 安全保证措施

1开工前召开安全专题会议,对施工人员进行安全教育培训,宣传安全生○

产的重要性,提高工人的安全意识。

2现场施工多为高空作业,○严格按照高空作业施工方案以及脚手架施工方案进行设施搭设,并按照相关要求采取安全防护措施。

3现场设置专职安全员,全面负责现场安全检查、监督工作,施工中要全○

天巡查,发现安全隐患立即停工整改,待排查隐患后再进行施工。

4材料进场要集中存放,对于易燃物品要有专人负责看管,并堆放场地要○

备有消防设备。

5高空人员每人配备安全绳和安全带各一套,○各种施工机具要与安全绳连接,防止坠落。

6雨雪天气不得施工。 ○

6 文明施工措施

1、进入施工现场人员严格遵守各种规章制度,不得打架斗殴。 ○

2、现场材料按照种类堆放整齐,不得乱放。 ○

3、施工作业面做到工完料尽,对于剩余的工程材料、废料分类存放到指○

定地点,每天完工后对作业面进行清理。

4、○生活区域和施工现场不得乱扔垃圾,尤其废料,不得对环境造成污染。


相关内容

  • 桥梁工程防腐涂装设计简介
  • 一.钢桥的特点及腐蚀危害 1.钢桥的特点 钢桥具有跨越能力大.强度高.建设速度快和施工期限短等特点. 我国自从1955年武汉长江大桥的建成,使万里长江耸立起中国人民征服长江的第一座丰碑,特别是20世纪90年代中期至今十几年来,随着国家基础设施建设速度的加快,在长江.黄河.珠江及其他河流上,大跨度钢桥 ...

  • 桥梁混凝土
  • 混凝土结构防腐涂装技术及发展趋势 张连军1,蓝席建1,袁泉利1李运德2,杨振波2, (1.宁波飞轮造漆有限责任公司,宁波 315000:2.北京航材百慕新材料技术工程股份公司,北京 100095) 摘 要:蓬勃发展钢筋混凝土结构基础设施以及工业设施为混凝土防腐涂料的发展提供了广阔的市场前景.介绍了桥 ...

  • 市政工程知识体系和质量关键点,推荐!
  • 最近有小伙伴提议说市政工程方面的资料推送太少,今日分享市政工程知识框架及质量控制点.还有小伙伴反映<室外工程>(12J003)链接失效,已更新,您可重新回复"室外图集"获取. 一.市政道路工程 1.路基 (1)检查现场施工质量,主要包括:填料质量:分层厚度:碾压质量等 ...

  • 桥梁的耐久性
  • <如何提高桥梁建筑的耐久性?> 一: 耐久性与设计 1.1 从设计观念上更新 从全球范围看, 结构工程学科在向时间域.空间域和学科基础三个方面发展. 1.2 按耐久性要求进行设计 耐久性的具体指标是指结构在正常设计.正常施工.正常使用.正常维修下的使用寿命, 所谓正常的设计, 一般指符合 ...

  • 建设工程质量检查要点
  • 建设工程质量检查要点 一.质量行为 1.建设(开发)单位 开发单位资质:开工前建设单位办理工程质量监督.施工图设计文件审查.施工许可(开工报告)以及有重大变更施工图设计文件的重新报审手续,与勘察.设计.施工.监理单位签定的承包合同及相关责任主体的资质等级,组织图纸会审.设计交底情况. 2.勘察.设计 ...

  • 高铁桥梁.路基地段声屏障施工方案
  • 目 录 1.编制说明 .................................................. 2 1.1编制目的 .......................................................... 2 1.2编制依据 ......... ...

  • 2015二建市政公用实务模拟试题
  • 1.单项选择题(共 20 题,每题 1 分,每题的备选项中,只有一个最正确或最符合题意.选对每题得 1 分,没选或错选均不得分) 规范将城市道路分为四类,它们是( ).主干路.次干路与支路. A.快速路 B.放射路 C.环路 D.过境路 标准答案: A答案解析:<城市道路设计规范>将城市 ...

  • 钢-混凝土组合梁的施工案例
  • 润扬大桥南接线工程丹徒互通主线桥大跨径钢--混凝土组合 梁的设计与施工 摘要:钢-混凝土组合梁具有良好的受力性能和较好的综合经济效益,应用前景广泛.纵向主要受力构件为钢箱梁,采用工厂预制现场拼接的施工工艺可以缩短工期,简化工地现场的施工工程量:横向由预应力混凝土构成桥面板及悬臂,有利于桥面沥青混凝土 ...

  • 武汉阳逻长江大桥锚碇设计
  • 公路 2004年12月 第12期 HIGHWAY Dec.2004 No.12 文章编号:0451-0712(2004)12-0039-08 中图分类号:U443.24 文献标识码:B 武汉阳逻长江大桥锚碇设计 刘明虎,徐国平,刘化图 (中交公路规划设计院 北京市 100010) 摘 要:武汉阳逻长 ...