联络通道开挖施工组织设计(台阶法)

深圳地铁一期工程2A 标段罗湖~国贸区间进站段

XK1+182.22~XK1+171.00段左线隧道

矿山法成洞施工程序

目 录

1. 工程概况 ................................................ 3

1.1 施工目的及工作范围 .................................................................................................. 3

1.2 隧道线路情况 .............................................................................................................. 3

1.3 工程地质 ...................................................................................................................... 4

1.4 工程重点及采取的相关措施 ...................................................................................... 6

2. 总体施工方案 ............................................ 8

2.1 施工组织顺序 .............................................................................................................. 8

2.2 施工现场布置 .............................................................................................................. 8

2.3 施工组织安排 .............................................................................................................. 8

3. 主要分项工程施工方法 ..................................... 9

3.1 洞门破除 ...................................................................................................................... 9

3.2 拱部超前小导管施工 .................................................................................................. 9

3.3 上台阶开挖 ................................................................................................................ 10

3.4 下台阶开挖 ................................................................................................................ 11

3.5 钢筋网敷设 ................................................................................................................ 11

3.6 格栅拱架施工 ............................................................................................................ 12

3.7 锁脚锚管施工 ............................................................................................................ 13

3.8 喷射混凝土 ................................................................................................................ 14

3.9 拱背回填注浆 ............................................................................................................ 15

3.10 开挖终点掌子面封闭 .............................................................................................. 16

3.11 混凝土导台施工....................................................................................................... 17

4. 隧道监控量测 ........................................... 18

4.1 监控量测的目的 ........................................................................................................ 18

4.2 监控量测计划 ............................................................................................................ 19

4.3 量测频率 .................................................................................................................... 21

5. 工期安排 ............................................... 23

5.1 开挖、支护循环时间及计划指标 ............................................................................ 23

5.2 进度计划安排 ............................................................................................................ 24

6. 劳动力安排 ............................................. 24

7. 主要机械设备 ........................................... 25

8. 质量保证措施 ........................................... 26

9. 施工安全保证措施........................................ 27

9.1 综合保证措施 ............................................................................................................ 27

9.2 施工现场安全技术措施 ............................................................................................ 28

附图:

1、罗国区间进站段工程地质剖面图

2、国贸站矿山法施工现场平面布置图

3、隧道开挖、支护结构断面图

4、隧道分步开挖断面示意图

5、掌子面封闭示意图

6、混凝土盾构导台示意图

7、混凝土盾构导台坡度及预埋件示意图

1. 工程概况

1.1 施工目的及工作范围

罗~国区间进站段区间进站段XK1+182.22~XK1+171.00段地质为超高强度的凝灰岩地层,根据原地质条件设计的1#盾构在同类岩层中的掘进情况,其掘进速度将非常缓慢,日进尺只能达到1m 左右,甚至更慢,其进度情况和业主总体计划的要求相差甚远。所以为了保证工程的总体进度,必须采取其它措施处理进站段超高强度的硬岩地层。即XK1+171.00为左线隧道盾构法和矿山法的里程分界处,1#盾构机仍以罗湖站明挖隧道为盾构工作井,由南向北掘进,而XK1+171.00~XK1+182.22共11.22m 采用矿山法成洞,以国贸站为工作井,由北向南施工。 最后盾构机穿越矿山隧道,进入国贸站。

目前工作井已形成,井口5t 桁吊可直接投入提升使用,施工场地、围挡已形成。工作内容包括:破除工作井壁、正洞开挖、初期支护、端头掌子面封闭、导台施工。

1.2 隧道线路情况

本区段隧道线路情况如下:

1、平曲线:为缓和曲线,曲线的参数方程为:

沿曲线起点处切线方向:X=L-L5/25.2/R2/L02

沿曲线起点处法线方向:Y=0.00000794X3-0.00000016X 2+0.00171X

式中L 0=34.999 R=599.940 L为起点到计算点的长度。

X 、Y 为局部坐标。

2、竖曲线:坡度为-2.98‰的直线。

详细的隧道线路设计参见“2A 标段盾构工程区间隧道(罗湖~国贸) 下行左线衬砌圆环布置图”,编号: 1/1/SA6/S/L01/WZO/QT/01001。

1.3 工程地质

为详细了解进站段的地质构成,查明坚硬岩层面的埋置深度,对进站段于2003年2月9日至2月15日进行了重新钻探。

本次钻孔布置以隧道中心线为准,并结合地下管线的埋设情况。孔距3~5米,共钻孔15个,其中7个钻孔为取土样孔,准确划分各岩土层的分界面,所钻孔为一般孔,以鉴分土层及坚硬基岩面的分界面为主,了解土层的分层为辅,钻孔深度约22.0米。

根据本次钻探,勘探范围内的地层主要为第四系填土层(Qml ) ,第四系冲洪积层(Qal+pl) ,第四系残积层(Qal ) ,基底为侏罗系中统(J2) 凝灰质

砂岩,现描述如下:

1、第四系填土层(Qml )

1) 填土:棕红、棕黄、褐灰色,松散,湿。表层为混凝土地面,其下主要为粘性土组成,含有强风化岩块,并夹有小量中风化岩块及石英,砂砾等,局部含有块石,碎石。厚度3.00~6.50米,层底标高3.65~

3.80米。

2、第四系冲洪积层(Qal+pl)

2-1) 粉土:灰色、灰绿色、灰黑色,由细砂和粘性土组成,上部含小量植物根,中、下部一般含细砂30~40%,湿,中密~密实,厚度0.40~1.90米,层顶标高-2.55~-0.30米。

2-2) 淤泥质土:灰黑色、灰色、软塑~流塑,顶部一般含15~30%细砂,厚度1.70~2.50米,层顶标高-3.25~0.80米。

2-3) 砾质粘土:灰色、褐黄色、棕红色,可塑,含大量粗砂砾,局部以砂为主。底部含较多卵石、砾石,厚度0.80~6.10米,顶层标高-5.35~1.50米。

3、第四系残积层(Qal )

3) 粉质粘土:棕红、棕黄、灰白色,可塑~硬塑,层部含砂量较多。由凝灰质砂岩风化残积而成,局部由细粒化岗岩风化而成,原岩结构隐约可见,局部夹强风化岩块。层厚3.40~3.60米,层顶标高-10.00~-6.05。

4、侏罗系中统(J2) 凝灰质砂岩

下伏基岩主要为凝灰质砂岩,局部受多次构造运动及岩浆侵入作用,变质形成混合岩,并伴随细粒花岗岩侵入。根据钻探,混合岩、细粒花岗岩已风花,中风化岩层为凝灰质砂岩。

4-1) 强风化岩:棕红、棕黄、浅灰色,岩芯呈土夹碎块状,碎块一般3~5cm ,裂隙发育,遇水易软化,厚度0.50~7.50米,层顶标高-14.25~-9.85米。

4-2) 中风化岩:灰绿色、青灰色,褐灰色,坚硬块状,隐晶质结构,钻探取岩芯破碎,岩体受多次构造运动作用,绿泥石化,硅化强,节理、裂隙发育,岩石中见不规则方解石细脉及石英细脉穿插,脉宽一般1~2mm ,局部1~2cm ,层厚0.80~8.04米,层顶标高-18.15~-8.95米。

根据勘察结果,强风化岩为碎块状,有遇水易软化特点。中风化岩为坚硬岩石,但由于构造运动作用,节理、裂隙发育,岩体较为破碎,钻进可取碎件。矿山法成洞处理范围主要为中风化凝灰岩。工程地质情况详见“罗国区间进站段工程地质剖面图”,编号:1/1/SA6/G/J01/WOO/QT/02046。

1.4 工程重点及采取的相关措施

本隧道只有11.22m ,隧道范围为中风化凝灰岩,强度较高。但穿越地段上软下硬,拱顶以上岩层较薄弱,再上部为强风化、粉质粘土、砾粘性土等。

所采取的相关措施如下:

1、详细了解、研究本段新钻探的地质资料,提前了解前方地质。根据地质情况提出实施方案。

2、制定和选用合理的施工方法。根据以往的施工经验,在不同地质条件下选用合理施工方法是防坍的重要手段。在制定和选择施工方法时注意以下几点:

(1)选定初期支护参数贯彻“宁强勿弱”的原则。对于介于两级围岩之间的按偏低的围岩级别进行支护。

(2)正确选用施工方法。上下台阶均采用人工(丁字镐、风镐、破碎机) 开挖,个别孤石和少量硬质岩采取风钻打眼、静态爆破解体,风镐修凿轮廓,尽量减少对围岩的扰动。其静态爆破的施工程序及化学炸药的有关资料,待购置后,根据厂家产品要求再进行补充该施工程序。

(3)开挖后自稳能力差的地段采用超前支护或超前加固前方围岩,

即坚持先护顶后开挖的原则组织施工。

(4)缩短各台阶开挖长度,使初期支护尽早封闭成环。

(5)施工过程中对围岩及支护结构进行变位量测,根据数据结合观察报告正确分析和支护的稳定性,并采取正确对策。

(6) 对变形超限的初期支护及时进行加固。

3、保证初期支护质量

(1)初期支护严格按施工技术规范施工,确保支护质量。

(2)提高开挖质量是保证支护质量是关键,不良地层应考虑超前支护。

(3)喷射混凝土与应围岩密贴,并保证喷混凝土强度,格栅拱架背后不允许有空洞,不许填片石和木材,喷混凝土将拱架完全覆盖。

(4)钢架间距符合设计要求,安装位置正确,保证接头处的等强连接,钢架置于原状土上。

(5)如需采取锚杆加固段,锚杆孔的长度,间距符合设计要求,保证杆孔内的砂浆饱满。

4、严格施工纪律。防坍的施工方案已经讨论确定,操作人员必须严格执行,不得私自变动,否则,无论后果如何,都要视为严重违章、对其进行严肃处理。

5、围岩含水地段先治水,后施工。

7、加强施工过程措施

(1)施工过程中确保各种措施、技术交底的落实,保证标准化作业。

(2)开挖过程中及时监控地质变化情况,指导现场施工。

2. 总体施工方案

2.1 施工组织顺序

①施工准备—→②洞门破除—→③上台阶开挖、支护(3m)—→④下台阶开挖、支护—→⑤掌子面封闭—→⑥隧道成形断面净空、轴线检查、验收—→⑦砼导台施工—→⑧工程验收。附“正洞开挖顺序示意图”,编号:1/1/SA6/G/J01/WOO/QT/02055。

2.2 施工现场布置

施工场地布置已完成,只增设暗挖部分所需的“空压机、沙石堆料场、水泥库、临时堆土场”等临时设施。场地布置详见“国贸站矿山法施工现场平面布置图”,编号:1/1/SA6/G/J01/WOO/QT/02047。

2.3 施工组织安排

进洞开挖前,先进行工作井连续墙井壁凿除,本工程量小,正洞只有11.22m ,但为保证初期支护尽早成环和工期要求,上台阶进洞3m 后开始下台阶施工,上下台阶平行作业。

1、开挖采用上下短台阶法施工,为满足上台阶拱部格栅钢架安装作业平台,上台阶长度保持在3~4m ,开挖遵循的原则:上下台阶均采用人工(丁字镐、风镐、破碎机) 开挖,或采取风钻打眼、静态爆破解体,风镐修凿轮廓。

2、上台阶出碴由人力手推车顺简易梭槽卸入隧底。隧底碴土由人工手推车运至工作井土斗,经目前已安装好的5t 桁吊提升至地面卸在临时堆土场。地面临时堆土场的碴土由人工配合装载机装入自卸汽车运

至指定点。

3、隧道断面、支护形式、施工方法见“隧道开挖、支护结构断面图”,编号:1/1/SA6/G/J01/WOO/QT/02048,以及“隧道分步开挖断面示意图”,编号:1/1/SA6/G/J01/WOO/QT/02049。

3. 主要分项工程施工方法

3.1 洞门破除

国贸站工作井井壁为600mm 厚钢筋混凝土,围护结构为800mm 厚钢筋混凝土连续墙,为了暗挖隧道正洞开挖的顺利实施,需将隧道开挖轮廓范围内洞门破除。

详细的施工程序参见“国贸站左线隧道洞门凿除施工程序”,编号:1/1/SA6/G/JO1/WOO/BT/00022-btb0071

3.2 拱部超前小导管施工(软弱围岩地层中使用)

1、拱部180°范围内设φ32×3.25普通水煤气管超前小导管预支护,环向间距300mm ,L=3000mm,外插角10~16°,每环搭接长度≥1000mm 。

2、施工组织顺序:①测量画出本环每根小导管位置→②风钻钻眼→③插入小导管→④连接注浆管→⑤堵塞孔口空隙→⑥注浆→⑦关闭导管口、拆除注浆系统。

3、施工方法

采用风钻钻孔,钻孔直径为43mm ,深度比导管插入长度约深2~3cm 。用人工锤击的方法将导管打入。个别不能打入的用风钻采用特制

钻杆将钢管顶入,注浆泵注浆。

4、主要技术措施

(1)按设计要求,在开挖掌子面准确画出本循环需设的小导管孔位。

(2)钻孔:采用风动凿岩机钻孔,成孔直径Φ43mm 。

(3)导管插入及孔口密封处理:钢管由人工插入或专用顶头顶进,顶进钻孔长度≮90%管长。管壁上钻小孔,以便浆液向围岩内压浆。钢管末端部焊设挡圈并用胶泥麻筋缠箍成楔形,以便钢管顶进孔后其外壁与孔岩壁间隙堵塞严密。钢管尾部外露足够长度,并与格栅钢拱架焊接在一起。钢管顶进时,注意保护管口不受损、变形,以便与注浆管路连接。

(4)注浆为水泥、水玻璃双液浆,通过实验及双液浆注浆的控制范围,确定浆液的稠度、注浆的实际配合比。要求浆液的凝固时间为15~20秒,同时浆液凝固后的强度在0.5~1MPa ,根据此参数,作浆液的配比试验。

(5)注浆:为加固隧道周边围岩,控制地表下沉,增大插管钢度,充填钢管周边空隙,对每根管棚进行注浆。注浆压力控制在0.5~1.0Mpa 。在注浆过程中,浆液应保持准确比例,不断搅动。

(6)注浆时做好记录,根据压力状况和跑浆情况确定终孔时间。

3.3 上台阶开挖

1、施工组织顺序:①超前小导管注浆(软弱围岩采用)→②测量放线→③上部环形导坑开挖→④钢筋网安装→⑤格栅拱架安装→⑥拱脚锁脚锚杆施工→⑦隐蔽检查验收→⑧喷射砼至设计厚度→⑨进入下

一循环。

2、在小导管形成的管棚支护下进行开挖,先进行环形导坑开挖、预留核心土,环形导坑的宽度以满足格栅拱架安装空间为准。采用人工(丁字镐、风镐) 开挖,遇到孤石时先将孤石四周用风镐凿除,不能凿除的孤石采取风钻打眼、膨胀炸药静态爆破解体,风镐修凿轮廓。

3、上台阶出碴由人力手推车卸入流槽卸入隧底。开挖完毕立即安设钢筋网片、格栅拱架安装、锁脚锚杆及喷射砼。

4、上台阶每循环开挖进尺0.7m ~1.0m(1榀格栅距离) 。

3.4 下台阶开挖

1、施工组织顺序:①测量放线→②土石开挖→③遇软弱围岩时先初喷砼约5cm →④钢筋网安装→⑤格栅拱架安装→⑥隐蔽检查验收→⑦喷射砼至设计厚度→⑧进入下一循环。

2、下台阶同样采用人工(丁字镐、风镐、破碎机) 开挖,或石采取风钻打眼、膨胀炸药静态爆破解体,风镐修凿轮廓;每循环开挖进尺为1~2榀格栅间距。

3、上、下台阶的渣土均需通过下台阶装运出洞,隧底采用人工手推车出渣。开挖完毕立即安设钢筋网片、格栅拱架安装及喷射砼。

3.5 钢筋网敷设

本隧道钢筋网采用A3、φ6钢筋,网格为15×15cm ,先在钢筋加工场地加工成4.2m ×1.0m 网片,现场人工安装,安装时将钢筋网绑扎在隧道轮廓前小导管或前一榀格栅钢架连接钢筋网上。网片间搭接长度≮20cm 。网片紧贴围岩面或初喷砼面铺贴。

3.6 格栅拱架施工

1、施工组织顺序:①测量画出钢架水平位置→②钢架分节就位→③调整钢架位置→④连接各节点→⑤定位固定、将钢架点焊在超前小导管或前一榀钢架纵向连接筋上→⑥焊接纵向连接筋→⑦隐蔽验收→⑧进入喷射砼工序。

2、格栅拱架制作安装

(1)绑扎好的格栅拱架使用前在加工场内进行试拼,将整个隧道轮廓各节拱架进行整体试拼,以检查连接部位是否吻合,加工误差符合规范要求。

(2)每榀钢拱架安装前,用经纬仪、水平仪准确测量定出拱架安装的中线、标高及拱脚设计位置。

(3)拱架安装由人工进行架立就位,拱脚必须架立在坚固的基座上。用短钢筋将拱架焊牢在锁脚锚杆上。

(4)绑扎纵向连接筋:按设计间距将各榀格栅焊接成整体。

(5)每榀钢架安装好后在其拱脚处按设计设置两根Φ32×3.25、L=3.0m锁脚锚管或岩层中使用锚杆固定,以限制拱架下沉,与钢架焊接牢固。在喷射砼完成后向管内注水泥、水玻璃双液浆加固。

3、主要技术措施

(1)开挖完成后,应立即安设格栅钢拱架。

(2)钢材质量和接头位置必须符合规范和设计要求。

(3)每榀钢架应绑扎牢固,无松动。

(4)为保证钢拱架的稳定和整体受力,设置纵向连接钢筋。连接筋

与钢拱架的连接点及已施工相邻拱架连接筋应焊接牢固。

(5)在初期支护形成“闭合”结构前,为减少初期支护下沉量,每个台阶安装钢拱架时,均应在拱脚设一块托板或其它硬垫,以增大受力面积,减少下沉量。

(6)格栅钢架和围岩尽量靠近,未进行初喷的应留2~3cm 间隙作混凝土保护层。当钢架和围岩的间隙过大时必须用喷射砼充填密实,不得用木材、片石等物体塞填。

(7)喷射砼应由两侧拱脚向上对称喷射,并将钢架覆盖。

3.7 锁脚锚管或锚杆施工

1、施工组织顺序:①锁脚锚管(杆)施作空间内核心土挖出→②画出本环锁脚锚管(杆)位置→③风钻钻眼→④插入钢管(杆)→⑤锚管连接注浆管→⑥喷射砼封闭孔口→⑦注浆→⑧关闭导管口、拆除注浆系统。

2、施工方法

锁脚锚杆在拱部格栅钢架安装完成后进行,钻孔前先挖出上台阶阻碍操作的核心土,采用风钻钻孔,钻孔直径为43mm ,深度比导管插入长度约深2~3cm 。用人工锤击的方法将导管打入。个别不能打入的用风钻采用特制钻杆将钢管(杆)顶入,锚管使用注浆泵注浆。

3、主要技术措施

上台阶每循环拱架两侧各设置2根,在格栅钢架安装完成后钻孔、拱部喷射砼完成封闭后再进行锚管注浆。其它技术措施同超前小导管主要技术措施相同。

3.8 喷射混凝土

1、集料要求

粗集料:碎石粒径不大于15mm 。

细集料:中砂或粗砂,细度模数大于2.5,含水率5%~7%。 加速凝剂:根据厂家提供的资料,提交给SYSTRA 。

2、施工顺序

①施工准备→②施喷面清理→③沙石、水泥、水计量配备→④搅拌机拌和→⑤装运喷料→⑥加速凝剂、现场施喷→⑦综合检查。

3、主要技术措施

(1)隧道开挖后围岩软弱段应立即对岩面初喷混凝土,以防岩体发生松弛。

(2)喷射混凝土前在钢筋网或钢架上每隔一定距离焊一短钢筋作为控制喷砼厚度的标。采用混凝土喷射机。

(3)施工机具布置在适当安全地带。

(4)喷射前对隧道轮廓进行处理,检查开挖净空尺寸。在不良地质地段,设专人随时观察围岩变化情况,当受喷面有涌水、淋水、集中出水点时,先进行引排水处理。

(5)用高压水冲洗受喷面,当受喷面遇水易软化时,用高压风吹净受喷面。

(6)加强喷射机组的日常检查和保养工作,经常检查电线路、设备和管路,使设备机良好,不致中途中断喷射作业。

(7)按施工前实验所取得的方法与条件进行喷射混凝土作业,在喷

射混凝土达到初凝后方能喷射下一层。首次喷射混凝土厚度应不小于50mm 。

(8)喷射作业分段、分片、分层,由下而上,从里到外顺序进行,有较大凹洼处,先喷射填平,先喷满钢架与岩面的空隙。

(9)喷嘴与受喷面保持垂直,距受喷面0.6~1.0m 。

(10)掌握好风压,减少回弹和粉尘,喷射压力0.15~0.2MPa 。

(11)施工中经常检查出料弯头、输料管和管路接头,处理故障时断电、停风,发现堵管时立即停风关机。

(12)在已有混凝土面上进行喷射时,应清除剥离部分,以保证新老混凝土之间具有良好的粘结强度。

(13)新喷射的混凝土应按规定洒水养护。

(14)喷射混凝土的回弹物不得重复利用,所有的回弹混凝土应从工作面清除。

3.9 拱背回填注浆(或有空洞)

1、为保证初期支护拱背密实,初期支护完成后,在拱背压注1:1水泥沙浆,强度在3MPa 。

2、在上台阶拱部格栅拱架安装完成、喷射砼前,沿隧道纵向每环格栅钢架预埋一环注浆管,上台阶每环共三榀拱架,在每榀拱架接头附近和中间位置各预埋一条注浆管(上台阶拱脚每侧各有两根锁脚锚管,不用预埋注浆管) 。即每环预埋5根注浆管,纵向环距2.4m 。注浆管采用φ32×3.25普通水煤气管,长600mm ,露出喷射砼面350mm 。注浆管预埋位置详见“隧道开挖、支护结构断面图”,编号:1/1/SA6/G/J01/WOO/QT/02048。

3、拱背回填注浆在每环拱架锁脚锚管注浆完成及初期支护喷射砼达到设计强度后再进行,拟采取施工完成进行一次回填注浆,注浆顺序:环向先两侧、后拱顶,纵向沿隧道开挖前进方向依次注浆。

4、拱背回填注浆技术措施同超前小导管和锁脚锚管注浆技术措施。

3.10 开挖终点掌子面封闭

本区间进站段盾构掘进方向与暗挖方向相反,为保证盾构在接近暗挖段时,不致于引起隧道坍塌、抵挡盾构掘进压力,暗挖完成后掌子面进行工字钢加网喷混凝土封闭。

1、当上台阶开挖至终点时,沿开挖轮廓打设一环超前小导管并注浆,以加固前方隧道上部围岩,同时探测前方隧道的围岩情况,其布置形式、长度、外插角等与暗挖段超前小导管相同。将掌子面基本修整成垂直面。再安设最后一环格栅钢架时,同时将水平、竖直工字钢架焊接在格栅钢架上。工字钢采用I20a 。整个隧道水平方向布置3道、竖直方向布置2道。铺设钢筋网两道,然后喷C20混凝土20cm 厚封闭掌子面。详见“掌子面封闭示意图”,编号:1/1/SA6/G/J01/WOO/QT/02050。

2、下台阶开挖至掌子面后,其封闭方案与上台阶同,竖向工字钢与上台阶焊接成整体,并在连接处两侧用10厚钢板帮焊加固。竖向同时与水平工字钢焊接成整体。

3、当盾构掘进接近掌子面时,逐步减小压力、减缓掘进速度,加强对掌子面观察,必要时采取量测监控,以合理调节盾构掘进速度。

4、如探测得知前方隧道的地质条件较差,则调整掌子面封闭措施,即增加正面水平注浆加固的措施。详细内容将根据实际情况再作调整,

并在后期施工时及时提供相应程序。

3.11 混凝土导台施工

1、导台设置

砼导台施工在掌子面封闭完成后进行,从开挖终点开始,反方向进行。全长11.02m 一次浇注完毕。导台的设计尺寸:范围为隧道底部60°,导台中部厚度为150mm ,两端为120mm ,导台混凝土强度为C30。导台各部尺寸详见“混凝土盾构导台示意图”,编号:1/1/SA6/G/J01/WOO/QT/02051。

2、施工工艺顺序

①测量放线→②锚钉安设→③内外侧顶面定位钢筋安装→④钢筋网铺设→⑤砼浇灌→⑥砼捣固、导台初步成型→⑦弧面成型抹光→⑧砼养护。

3、测量放线

导台两侧顶面施工与线路曲线吻合,放线时按中线里程每5m 放出内、外侧定位点(边线及高程) 。采用两条ф22钢筋按定位点用短钢筋焊接、固定在初衬格栅钢架上,形成导台内、外侧顶面控制线,作为导台抹面控制标志。以此利用自制成形器赶平混凝土和对成形的弧面进行检查。

4、导台锚钉及钢筋网安设

放线完成后,为防止盾构推进时,导台与初衬面产生相对滑动、增加导台抗压强度及便于安设钢筋网,在喷射混凝土和导台接触面增设Φ

20、L=300mm锚钉,横向每断面3根,纵向间距600mm 。锚钉伸入喷射混凝土不小于150mm 。顶面距导台面(保护层)35mm 。采用冲击电钻钻φ

20孔,人工锤击打入喷射混凝土,通过混凝土浇注后浆液渗透达到减易植筋效果。钢筋网为φ6、200×200网孔,距导台弧形顶面(保护层)35mm ,在加工场先加工成3484×5000mm 网片,铺设时将网片按弧面点焊在锚钉上。

5、混凝土浇注

导台混凝土采用商品混凝土,浇注前一天通知商品混凝土供应商预计浇注时间、方量,正洞每延米约0.81m 3/m,洞内采用人工手推车运输、人工浇捣,每一段浇捣反方向进行,手推车运输采用在锚钉上铺木板形成运输通道。

混凝土浇捣过程中,每捣实初步成形一段,利用“自制成形器”成形弧面,然后人工抹平、抹光,再用成形器检查、抹平、抹光,如此反复,直到导台弧面达到要求为止。

6、导台与盾构切口连接处施工

为了保证盾构顺利上到导台上,在接口处的2m 长的导台坡度作微量调整,由原设计的-2.98‰改为+7‰,接口处高程降低20mm ,2m 后的导台恢复至原设计坡度和设计高程。而且导台边缘预埋840×700×10mm 钢板,加强导台边缘的强度。详见“混凝土盾构导台坡度及预埋件示意图”,编号:1/1/SA6/G/J01/WOO/QT/02052。

4. 隧道监控量测

4.1 监控量测的目的

实施监控量测的目的具体包括:

1、通过监控量测了解各施工阶段地层与支护结构的动态变化,把

握施工过程中结构所处的安全状态,判断围岩稳定性,支护可靠性。

2、用现场实测的结果弥补理论分析过程中存在的不足,并把监测结果反馈设计、指导施工。为修改施工方法、调整围岩级别、变更支护设计参数提供依据。

3、通过监控量测对工程施工可能产生的环境影响进行全面的监控。

4、通过监控量测进行隧道日常的施工管理,确保施工安全和质量。

5、通过监控量测了解该工程条件下所表现、反映出来的一些地下工程规律和特点,为今后类似工程或该工法本身的发展提供借鉴、依据和指导作用。

4.2 监控量测计划

监控量测的项目主要根据隧道工程的地质条件、围岩类别、跨度、埋深、开挖方法和支护类型等综合确定。而且,在隧道工程中进行量测,绝不是单纯地为了获取信息,而是把它作为施工管理的一个积极有效的手段,因此量测信息应能:

确切地预报破坏和变形等未来的动态,对设计参数和施工流程加以监控,以便及时掌握围岩动态而采取适当的措施(如预估最终位移值、根据监控基准调整、修改开挖和支护的顺序和时机等)。

满足作为设计变更的重要信息和各项要求,如提供设计、施工所需的重要参数(初始位移速度、作用荷载等)。

根据以上所述并结合本隧道的实际情况,拟进行A 类:洞内外观察、地表下沉、拱顶下沉等项目的施工监测项目。监测内容见下表:

监控量测项目一览表

主要监控量测项目简介如下:

1、洞内外观察

地质和支护状态观察包括工作面观察和支护结构的支护效果观察。

(1)观察频率:

每一循环进尺,都必须进行一次工作面观察,并作好客观详尽的记录。在地质变化不大地段,可每天按一个工作面记录,对已成洞地段主要是支护效果的观察,频率同工作面。

(2)观察内容:

1) 工作面工程地质和水文地质情况观察和描述:包括岩石名称,岩石产状,风化变质情况,断层、层理、节理等结构面的分布、走向、产状及频率,有无偏压或膨胀地压,工作面及毛洞自稳情况,地下水情况及影响等内容。

2) 工作面附近初期支护状态观察和已成洞的支护效果观察:包括喷

层开裂部位、宽度、长度及深度,防水效果等。

2、拱顶下沉量测

(1)量测目的:监视隧道拱顶的绝对下沉量,掌握断面的变形动态,判断支护结构的稳定性。

(2)量测方法:用全站仪进行隧道拱顶下沉量测。

沿隧道拱顶部每隔5米布设测点,2次/天,工作面开挖后及时埋测点。

3、地表下沉量测

(1)量测目的:隧道开挖时必然引起地面沉陷,量测的目的是了解: 1) 地面下沉范围,量值; 2) 地面下沉随工作面推进的规律; 3) 地面下沉稳定的时间。 (2)量测方法:

一般用精密水准仪量测,仪器精度±0.1mm 。

测点沿纵向(隧道中线方向)布置,其间距为5~6m ,并布设一个横断面,每断面布置7个测点即可。测点应在开挖形成的下沉之前埋设,一直测到下沉稳定。详细参见国贸站进站段盾构隧道施工沉降测点布置。

4.3 量测频率

1、量测频率

量测频率根据监测数据的变化情况而定,一般按下表进行。

量测频率表

2、监测数据的分析及预测

取得监测数据后,及时进行整理,绘制位移随时间或空间的变化曲线图。在取得足够数据后,还应根据散点图的数据分布情况,选择合适的函数,对监测结果进行回归,以预测该测点可能出现的最终位移值及结构的安全性,评价施工方法,确定工程措施。

3、监测数据的信息反馈

为确保监测结果质量,加快信息反馈速度,全部监测数据均有计算机管理,并绘制测点位移变化曲线图。

(1)信息反馈修正设计的基本要求

1) 现代隧道施工时,设计、施工必须紧密配合,共同研究,综合分析各项施工信息,及时进行信息反馈,最终确定和修改设计。

2) 信息反馈修正设计,系指在隧道开挖后,根据施工信息,对施工前预设计所确定的结构形式、支护参数、预留变形量、施工工艺、施工方法以及各工序施作的时间等的检验和修正,是贯穿于整个施工过程的设计阶段。

3)施工信息是指施工观察、现场地质调查、现场监控量测等得到的数据和信息。施工信息是隧道开挖后围岩稳定性的动态反映,也是修正设计的依据。对各种信息进行综合分析、互相印证,对预设计参数修正

和施工方法的改进是不可缺少的部分

(2)施工信息的应用

根据一个量测断面的施工信息综合分析处理结果,进行设计参数修正。

5. 工期安排

5.1 开挖、支护循环时间及计划指标

1、上台阶开挖、支护循环时间

上台阶开挖、支护循环时间表

每循环进尺0.7m(1榀格栅间距) 。

计划指标:每循环0.7m/17小时。计划日进尺:1m/天。

2、下台阶开挖、支护循环时间

下台阶开挖、支护循环时间表

每循环进尺0.7m(1榀格栅间距) 。

计划指标:每循环0.7m/16.5小时。计划日进尺:1.0m/天。

5.2 进度计划安排

详细工期安排见《进度计划时间表》。

6. 劳动力安排

根据本区段工程情况,抽派我公司原在深圳地铁一期工程2A 标段

购香区间右线XK9+914.792~XK10+034.792段矿山法成洞施工的全套施工、管理人员,具有相同工程的施工经验。配备劳动力详见下表:

投入劳动力表

7. 主要机械设备

主要机械设备计划表

8. 质量保证措施

1、开工前认真熟悉施工文件,计算出隧道各主要部位的标高,制定《标高表》,上报监理工程师审核后,作为施工测量的依据。

2、喷射砼前,检查开挖断面尺寸、清除杂物和松动岩体,埋设短节钢筋,以标识喷砼厚度,用高压风、高压水清洗受喷面,喷射作业分段、分片、分块、分层自下而上进行,喷射砼紧跟开挖工作面。

3、加强原材料的进货检验,把好进货关,所有材料存放及使用均标识、记录清楚,确保不合格材料不投入工程实体使用中,并且有追溯性,在施工前,需将所有有关材料特性资料提交SYSTRA 。

4、实行质量责任制,逐级落实到工班,责任到人。把工程质量和职工的奖金、评先等紧密挂钩,奖罚分明,增强工人的责任感。

5、喷砼用外加剂经试验选定质优品牌,确定最佳掺量,同时需SYSTRA 参与试验。

6、对空气湿度进行监测,当空气湿度不能满足养生要求时,必须进行喷水养护。

7、严格施工过程的质量控制

9. 施工安全保证措施 9.1 综合保证措施

1、建立以岗位责任制为中心的安全生产逐级负责制,制度明确、责任到人,奖罚分明。

2、按施工人员的比例配备足够的专职安全员,驻地管理人员一律佩证上岗,安全员佩证为红色,以示醒目。

3、在编制施工计划的同时,编制详细的安全操作规程、细则、制度及切实可行的安全技术措施,分发至工班,组织逐条落实。搞好“五同时”(即在计划、布置、检查、总结、评比生产的同时,计划、布置、检查、总结、评比安全工作) 和“三级安全教育”。

4、每一工序开始前,做出详细的施工方案和实施措施,及时做好施工技术及安全技术交底,并在施工过程中督促检查,严格坚持特殊工种持证上岗。

5、进行定期和不定期的安全检查,及时发现和解决不安全的事故隐患,杜绝违章作业和违章指挥现象,同时加大安全教育及宣传力度。

6、坚持每周一安全活动日的安全学习制度。严格执行交接班制度,坚持工前讲安全、工中检查安全、工后评比安全的“三工制”活动。

7、开工前期制定各项安全制度及防护措施: (1)各类机电设备操作规程及各项安全作业规章制度。 (2)用电安全须知及电力架设、养护作业制度。 (3)风、水管路安设及养护制度。 (4)防雷电、防洪、防火的安全专项规定。

8、针对关键工序,编制专项安全措施和专项技术交底,并设专人进行安全监督与落实,共设3名安全员负责施工安全,具体人员:毛节成,倪新龙,刘建平。

9、做好现场医护和急救工作。

9.2 施工现场安全技术措施

1、施工现场的布置符合防火、防爆、防洪、防雷电等安全规定及文明施工的要求。施工现场的生产、生活办公用房、仓库、材料堆放场、修理场应按批准的总平面布置图进行布置。

2、现场道路平整、坚实、保持畅通,危险地点悬挂安全标志,符合安全规定的标牌,施工现场设置大幅安全宣传标语。

3、现场的生产、生活区设足够的消防水源和消防设施网点,消防器有专人管理,不乱拿乱放,所有施工人员要熟悉并掌握消防设备的性能和使用方法。

4、各类房屋、库棚、料场等安全消防距离符合有关规定,现场的易燃杂物随时清理,严禁在有火种的场所或其近旁堆放易燃物品。

5、施工现场的临时用电严格按照《施工现场临时用电安全技术规范》JGJ6-88的规定执行。

6、施工中如发现危及地面建筑物或有危险品时立即停止施工,待处理完毕后方可施工。

7、从事电力、高处作业及起重作业等特殊作业人员,各种机械的操作人员及机动车辆驾驶人员,必须经过劳动部门专业培训并考试取得合格证后,方准持证独立操作。

8、施工现场设立安全标志。危险地区必须悬挂“危险”或“禁止通行”、“严禁烟火”等标志,夜间设红灯警示。

深圳地铁一期工程2A 标段罗湖~国贸区间进站段

XK1+182.22~XK1+171.00段左线隧道

矿山法成洞施工程序

目 录

1. 工程概况 ................................................ 3

1.1 施工目的及工作范围 .................................................................................................. 3

1.2 隧道线路情况 .............................................................................................................. 3

1.3 工程地质 ...................................................................................................................... 4

1.4 工程重点及采取的相关措施 ...................................................................................... 6

2. 总体施工方案 ............................................ 8

2.1 施工组织顺序 .............................................................................................................. 8

2.2 施工现场布置 .............................................................................................................. 8

2.3 施工组织安排 .............................................................................................................. 8

3. 主要分项工程施工方法 ..................................... 9

3.1 洞门破除 ...................................................................................................................... 9

3.2 拱部超前小导管施工 .................................................................................................. 9

3.3 上台阶开挖 ................................................................................................................ 10

3.4 下台阶开挖 ................................................................................................................ 11

3.5 钢筋网敷设 ................................................................................................................ 11

3.6 格栅拱架施工 ............................................................................................................ 12

3.7 锁脚锚管施工 ............................................................................................................ 13

3.8 喷射混凝土 ................................................................................................................ 14

3.9 拱背回填注浆 ............................................................................................................ 15

3.10 开挖终点掌子面封闭 .............................................................................................. 16

3.11 混凝土导台施工....................................................................................................... 17

4. 隧道监控量测 ........................................... 18

4.1 监控量测的目的 ........................................................................................................ 18

4.2 监控量测计划 ............................................................................................................ 19

4.3 量测频率 .................................................................................................................... 21

5. 工期安排 ............................................... 23

5.1 开挖、支护循环时间及计划指标 ............................................................................ 23

5.2 进度计划安排 ............................................................................................................ 24

6. 劳动力安排 ............................................. 24

7. 主要机械设备 ........................................... 25

8. 质量保证措施 ........................................... 26

9. 施工安全保证措施........................................ 27

9.1 综合保证措施 ............................................................................................................ 27

9.2 施工现场安全技术措施 ............................................................................................ 28

附图:

1、罗国区间进站段工程地质剖面图

2、国贸站矿山法施工现场平面布置图

3、隧道开挖、支护结构断面图

4、隧道分步开挖断面示意图

5、掌子面封闭示意图

6、混凝土盾构导台示意图

7、混凝土盾构导台坡度及预埋件示意图

1. 工程概况

1.1 施工目的及工作范围

罗~国区间进站段区间进站段XK1+182.22~XK1+171.00段地质为超高强度的凝灰岩地层,根据原地质条件设计的1#盾构在同类岩层中的掘进情况,其掘进速度将非常缓慢,日进尺只能达到1m 左右,甚至更慢,其进度情况和业主总体计划的要求相差甚远。所以为了保证工程的总体进度,必须采取其它措施处理进站段超高强度的硬岩地层。即XK1+171.00为左线隧道盾构法和矿山法的里程分界处,1#盾构机仍以罗湖站明挖隧道为盾构工作井,由南向北掘进,而XK1+171.00~XK1+182.22共11.22m 采用矿山法成洞,以国贸站为工作井,由北向南施工。 最后盾构机穿越矿山隧道,进入国贸站。

目前工作井已形成,井口5t 桁吊可直接投入提升使用,施工场地、围挡已形成。工作内容包括:破除工作井壁、正洞开挖、初期支护、端头掌子面封闭、导台施工。

1.2 隧道线路情况

本区段隧道线路情况如下:

1、平曲线:为缓和曲线,曲线的参数方程为:

沿曲线起点处切线方向:X=L-L5/25.2/R2/L02

沿曲线起点处法线方向:Y=0.00000794X3-0.00000016X 2+0.00171X

式中L 0=34.999 R=599.940 L为起点到计算点的长度。

X 、Y 为局部坐标。

2、竖曲线:坡度为-2.98‰的直线。

详细的隧道线路设计参见“2A 标段盾构工程区间隧道(罗湖~国贸) 下行左线衬砌圆环布置图”,编号: 1/1/SA6/S/L01/WZO/QT/01001。

1.3 工程地质

为详细了解进站段的地质构成,查明坚硬岩层面的埋置深度,对进站段于2003年2月9日至2月15日进行了重新钻探。

本次钻孔布置以隧道中心线为准,并结合地下管线的埋设情况。孔距3~5米,共钻孔15个,其中7个钻孔为取土样孔,准确划分各岩土层的分界面,所钻孔为一般孔,以鉴分土层及坚硬基岩面的分界面为主,了解土层的分层为辅,钻孔深度约22.0米。

根据本次钻探,勘探范围内的地层主要为第四系填土层(Qml ) ,第四系冲洪积层(Qal+pl) ,第四系残积层(Qal ) ,基底为侏罗系中统(J2) 凝灰质

砂岩,现描述如下:

1、第四系填土层(Qml )

1) 填土:棕红、棕黄、褐灰色,松散,湿。表层为混凝土地面,其下主要为粘性土组成,含有强风化岩块,并夹有小量中风化岩块及石英,砂砾等,局部含有块石,碎石。厚度3.00~6.50米,层底标高3.65~

3.80米。

2、第四系冲洪积层(Qal+pl)

2-1) 粉土:灰色、灰绿色、灰黑色,由细砂和粘性土组成,上部含小量植物根,中、下部一般含细砂30~40%,湿,中密~密实,厚度0.40~1.90米,层顶标高-2.55~-0.30米。

2-2) 淤泥质土:灰黑色、灰色、软塑~流塑,顶部一般含15~30%细砂,厚度1.70~2.50米,层顶标高-3.25~0.80米。

2-3) 砾质粘土:灰色、褐黄色、棕红色,可塑,含大量粗砂砾,局部以砂为主。底部含较多卵石、砾石,厚度0.80~6.10米,顶层标高-5.35~1.50米。

3、第四系残积层(Qal )

3) 粉质粘土:棕红、棕黄、灰白色,可塑~硬塑,层部含砂量较多。由凝灰质砂岩风化残积而成,局部由细粒化岗岩风化而成,原岩结构隐约可见,局部夹强风化岩块。层厚3.40~3.60米,层顶标高-10.00~-6.05。

4、侏罗系中统(J2) 凝灰质砂岩

下伏基岩主要为凝灰质砂岩,局部受多次构造运动及岩浆侵入作用,变质形成混合岩,并伴随细粒花岗岩侵入。根据钻探,混合岩、细粒花岗岩已风花,中风化岩层为凝灰质砂岩。

4-1) 强风化岩:棕红、棕黄、浅灰色,岩芯呈土夹碎块状,碎块一般3~5cm ,裂隙发育,遇水易软化,厚度0.50~7.50米,层顶标高-14.25~-9.85米。

4-2) 中风化岩:灰绿色、青灰色,褐灰色,坚硬块状,隐晶质结构,钻探取岩芯破碎,岩体受多次构造运动作用,绿泥石化,硅化强,节理、裂隙发育,岩石中见不规则方解石细脉及石英细脉穿插,脉宽一般1~2mm ,局部1~2cm ,层厚0.80~8.04米,层顶标高-18.15~-8.95米。

根据勘察结果,强风化岩为碎块状,有遇水易软化特点。中风化岩为坚硬岩石,但由于构造运动作用,节理、裂隙发育,岩体较为破碎,钻进可取碎件。矿山法成洞处理范围主要为中风化凝灰岩。工程地质情况详见“罗国区间进站段工程地质剖面图”,编号:1/1/SA6/G/J01/WOO/QT/02046。

1.4 工程重点及采取的相关措施

本隧道只有11.22m ,隧道范围为中风化凝灰岩,强度较高。但穿越地段上软下硬,拱顶以上岩层较薄弱,再上部为强风化、粉质粘土、砾粘性土等。

所采取的相关措施如下:

1、详细了解、研究本段新钻探的地质资料,提前了解前方地质。根据地质情况提出实施方案。

2、制定和选用合理的施工方法。根据以往的施工经验,在不同地质条件下选用合理施工方法是防坍的重要手段。在制定和选择施工方法时注意以下几点:

(1)选定初期支护参数贯彻“宁强勿弱”的原则。对于介于两级围岩之间的按偏低的围岩级别进行支护。

(2)正确选用施工方法。上下台阶均采用人工(丁字镐、风镐、破碎机) 开挖,个别孤石和少量硬质岩采取风钻打眼、静态爆破解体,风镐修凿轮廓,尽量减少对围岩的扰动。其静态爆破的施工程序及化学炸药的有关资料,待购置后,根据厂家产品要求再进行补充该施工程序。

(3)开挖后自稳能力差的地段采用超前支护或超前加固前方围岩,

即坚持先护顶后开挖的原则组织施工。

(4)缩短各台阶开挖长度,使初期支护尽早封闭成环。

(5)施工过程中对围岩及支护结构进行变位量测,根据数据结合观察报告正确分析和支护的稳定性,并采取正确对策。

(6) 对变形超限的初期支护及时进行加固。

3、保证初期支护质量

(1)初期支护严格按施工技术规范施工,确保支护质量。

(2)提高开挖质量是保证支护质量是关键,不良地层应考虑超前支护。

(3)喷射混凝土与应围岩密贴,并保证喷混凝土强度,格栅拱架背后不允许有空洞,不许填片石和木材,喷混凝土将拱架完全覆盖。

(4)钢架间距符合设计要求,安装位置正确,保证接头处的等强连接,钢架置于原状土上。

(5)如需采取锚杆加固段,锚杆孔的长度,间距符合设计要求,保证杆孔内的砂浆饱满。

4、严格施工纪律。防坍的施工方案已经讨论确定,操作人员必须严格执行,不得私自变动,否则,无论后果如何,都要视为严重违章、对其进行严肃处理。

5、围岩含水地段先治水,后施工。

7、加强施工过程措施

(1)施工过程中确保各种措施、技术交底的落实,保证标准化作业。

(2)开挖过程中及时监控地质变化情况,指导现场施工。

2. 总体施工方案

2.1 施工组织顺序

①施工准备—→②洞门破除—→③上台阶开挖、支护(3m)—→④下台阶开挖、支护—→⑤掌子面封闭—→⑥隧道成形断面净空、轴线检查、验收—→⑦砼导台施工—→⑧工程验收。附“正洞开挖顺序示意图”,编号:1/1/SA6/G/J01/WOO/QT/02055。

2.2 施工现场布置

施工场地布置已完成,只增设暗挖部分所需的“空压机、沙石堆料场、水泥库、临时堆土场”等临时设施。场地布置详见“国贸站矿山法施工现场平面布置图”,编号:1/1/SA6/G/J01/WOO/QT/02047。

2.3 施工组织安排

进洞开挖前,先进行工作井连续墙井壁凿除,本工程量小,正洞只有11.22m ,但为保证初期支护尽早成环和工期要求,上台阶进洞3m 后开始下台阶施工,上下台阶平行作业。

1、开挖采用上下短台阶法施工,为满足上台阶拱部格栅钢架安装作业平台,上台阶长度保持在3~4m ,开挖遵循的原则:上下台阶均采用人工(丁字镐、风镐、破碎机) 开挖,或采取风钻打眼、静态爆破解体,风镐修凿轮廓。

2、上台阶出碴由人力手推车顺简易梭槽卸入隧底。隧底碴土由人工手推车运至工作井土斗,经目前已安装好的5t 桁吊提升至地面卸在临时堆土场。地面临时堆土场的碴土由人工配合装载机装入自卸汽车运

至指定点。

3、隧道断面、支护形式、施工方法见“隧道开挖、支护结构断面图”,编号:1/1/SA6/G/J01/WOO/QT/02048,以及“隧道分步开挖断面示意图”,编号:1/1/SA6/G/J01/WOO/QT/02049。

3. 主要分项工程施工方法

3.1 洞门破除

国贸站工作井井壁为600mm 厚钢筋混凝土,围护结构为800mm 厚钢筋混凝土连续墙,为了暗挖隧道正洞开挖的顺利实施,需将隧道开挖轮廓范围内洞门破除。

详细的施工程序参见“国贸站左线隧道洞门凿除施工程序”,编号:1/1/SA6/G/JO1/WOO/BT/00022-btb0071

3.2 拱部超前小导管施工(软弱围岩地层中使用)

1、拱部180°范围内设φ32×3.25普通水煤气管超前小导管预支护,环向间距300mm ,L=3000mm,外插角10~16°,每环搭接长度≥1000mm 。

2、施工组织顺序:①测量画出本环每根小导管位置→②风钻钻眼→③插入小导管→④连接注浆管→⑤堵塞孔口空隙→⑥注浆→⑦关闭导管口、拆除注浆系统。

3、施工方法

采用风钻钻孔,钻孔直径为43mm ,深度比导管插入长度约深2~3cm 。用人工锤击的方法将导管打入。个别不能打入的用风钻采用特制

钻杆将钢管顶入,注浆泵注浆。

4、主要技术措施

(1)按设计要求,在开挖掌子面准确画出本循环需设的小导管孔位。

(2)钻孔:采用风动凿岩机钻孔,成孔直径Φ43mm 。

(3)导管插入及孔口密封处理:钢管由人工插入或专用顶头顶进,顶进钻孔长度≮90%管长。管壁上钻小孔,以便浆液向围岩内压浆。钢管末端部焊设挡圈并用胶泥麻筋缠箍成楔形,以便钢管顶进孔后其外壁与孔岩壁间隙堵塞严密。钢管尾部外露足够长度,并与格栅钢拱架焊接在一起。钢管顶进时,注意保护管口不受损、变形,以便与注浆管路连接。

(4)注浆为水泥、水玻璃双液浆,通过实验及双液浆注浆的控制范围,确定浆液的稠度、注浆的实际配合比。要求浆液的凝固时间为15~20秒,同时浆液凝固后的强度在0.5~1MPa ,根据此参数,作浆液的配比试验。

(5)注浆:为加固隧道周边围岩,控制地表下沉,增大插管钢度,充填钢管周边空隙,对每根管棚进行注浆。注浆压力控制在0.5~1.0Mpa 。在注浆过程中,浆液应保持准确比例,不断搅动。

(6)注浆时做好记录,根据压力状况和跑浆情况确定终孔时间。

3.3 上台阶开挖

1、施工组织顺序:①超前小导管注浆(软弱围岩采用)→②测量放线→③上部环形导坑开挖→④钢筋网安装→⑤格栅拱架安装→⑥拱脚锁脚锚杆施工→⑦隐蔽检查验收→⑧喷射砼至设计厚度→⑨进入下

一循环。

2、在小导管形成的管棚支护下进行开挖,先进行环形导坑开挖、预留核心土,环形导坑的宽度以满足格栅拱架安装空间为准。采用人工(丁字镐、风镐) 开挖,遇到孤石时先将孤石四周用风镐凿除,不能凿除的孤石采取风钻打眼、膨胀炸药静态爆破解体,风镐修凿轮廓。

3、上台阶出碴由人力手推车卸入流槽卸入隧底。开挖完毕立即安设钢筋网片、格栅拱架安装、锁脚锚杆及喷射砼。

4、上台阶每循环开挖进尺0.7m ~1.0m(1榀格栅距离) 。

3.4 下台阶开挖

1、施工组织顺序:①测量放线→②土石开挖→③遇软弱围岩时先初喷砼约5cm →④钢筋网安装→⑤格栅拱架安装→⑥隐蔽检查验收→⑦喷射砼至设计厚度→⑧进入下一循环。

2、下台阶同样采用人工(丁字镐、风镐、破碎机) 开挖,或石采取风钻打眼、膨胀炸药静态爆破解体,风镐修凿轮廓;每循环开挖进尺为1~2榀格栅间距。

3、上、下台阶的渣土均需通过下台阶装运出洞,隧底采用人工手推车出渣。开挖完毕立即安设钢筋网片、格栅拱架安装及喷射砼。

3.5 钢筋网敷设

本隧道钢筋网采用A3、φ6钢筋,网格为15×15cm ,先在钢筋加工场地加工成4.2m ×1.0m 网片,现场人工安装,安装时将钢筋网绑扎在隧道轮廓前小导管或前一榀格栅钢架连接钢筋网上。网片间搭接长度≮20cm 。网片紧贴围岩面或初喷砼面铺贴。

3.6 格栅拱架施工

1、施工组织顺序:①测量画出钢架水平位置→②钢架分节就位→③调整钢架位置→④连接各节点→⑤定位固定、将钢架点焊在超前小导管或前一榀钢架纵向连接筋上→⑥焊接纵向连接筋→⑦隐蔽验收→⑧进入喷射砼工序。

2、格栅拱架制作安装

(1)绑扎好的格栅拱架使用前在加工场内进行试拼,将整个隧道轮廓各节拱架进行整体试拼,以检查连接部位是否吻合,加工误差符合规范要求。

(2)每榀钢拱架安装前,用经纬仪、水平仪准确测量定出拱架安装的中线、标高及拱脚设计位置。

(3)拱架安装由人工进行架立就位,拱脚必须架立在坚固的基座上。用短钢筋将拱架焊牢在锁脚锚杆上。

(4)绑扎纵向连接筋:按设计间距将各榀格栅焊接成整体。

(5)每榀钢架安装好后在其拱脚处按设计设置两根Φ32×3.25、L=3.0m锁脚锚管或岩层中使用锚杆固定,以限制拱架下沉,与钢架焊接牢固。在喷射砼完成后向管内注水泥、水玻璃双液浆加固。

3、主要技术措施

(1)开挖完成后,应立即安设格栅钢拱架。

(2)钢材质量和接头位置必须符合规范和设计要求。

(3)每榀钢架应绑扎牢固,无松动。

(4)为保证钢拱架的稳定和整体受力,设置纵向连接钢筋。连接筋

与钢拱架的连接点及已施工相邻拱架连接筋应焊接牢固。

(5)在初期支护形成“闭合”结构前,为减少初期支护下沉量,每个台阶安装钢拱架时,均应在拱脚设一块托板或其它硬垫,以增大受力面积,减少下沉量。

(6)格栅钢架和围岩尽量靠近,未进行初喷的应留2~3cm 间隙作混凝土保护层。当钢架和围岩的间隙过大时必须用喷射砼充填密实,不得用木材、片石等物体塞填。

(7)喷射砼应由两侧拱脚向上对称喷射,并将钢架覆盖。

3.7 锁脚锚管或锚杆施工

1、施工组织顺序:①锁脚锚管(杆)施作空间内核心土挖出→②画出本环锁脚锚管(杆)位置→③风钻钻眼→④插入钢管(杆)→⑤锚管连接注浆管→⑥喷射砼封闭孔口→⑦注浆→⑧关闭导管口、拆除注浆系统。

2、施工方法

锁脚锚杆在拱部格栅钢架安装完成后进行,钻孔前先挖出上台阶阻碍操作的核心土,采用风钻钻孔,钻孔直径为43mm ,深度比导管插入长度约深2~3cm 。用人工锤击的方法将导管打入。个别不能打入的用风钻采用特制钻杆将钢管(杆)顶入,锚管使用注浆泵注浆。

3、主要技术措施

上台阶每循环拱架两侧各设置2根,在格栅钢架安装完成后钻孔、拱部喷射砼完成封闭后再进行锚管注浆。其它技术措施同超前小导管主要技术措施相同。

3.8 喷射混凝土

1、集料要求

粗集料:碎石粒径不大于15mm 。

细集料:中砂或粗砂,细度模数大于2.5,含水率5%~7%。 加速凝剂:根据厂家提供的资料,提交给SYSTRA 。

2、施工顺序

①施工准备→②施喷面清理→③沙石、水泥、水计量配备→④搅拌机拌和→⑤装运喷料→⑥加速凝剂、现场施喷→⑦综合检查。

3、主要技术措施

(1)隧道开挖后围岩软弱段应立即对岩面初喷混凝土,以防岩体发生松弛。

(2)喷射混凝土前在钢筋网或钢架上每隔一定距离焊一短钢筋作为控制喷砼厚度的标。采用混凝土喷射机。

(3)施工机具布置在适当安全地带。

(4)喷射前对隧道轮廓进行处理,检查开挖净空尺寸。在不良地质地段,设专人随时观察围岩变化情况,当受喷面有涌水、淋水、集中出水点时,先进行引排水处理。

(5)用高压水冲洗受喷面,当受喷面遇水易软化时,用高压风吹净受喷面。

(6)加强喷射机组的日常检查和保养工作,经常检查电线路、设备和管路,使设备机良好,不致中途中断喷射作业。

(7)按施工前实验所取得的方法与条件进行喷射混凝土作业,在喷

射混凝土达到初凝后方能喷射下一层。首次喷射混凝土厚度应不小于50mm 。

(8)喷射作业分段、分片、分层,由下而上,从里到外顺序进行,有较大凹洼处,先喷射填平,先喷满钢架与岩面的空隙。

(9)喷嘴与受喷面保持垂直,距受喷面0.6~1.0m 。

(10)掌握好风压,减少回弹和粉尘,喷射压力0.15~0.2MPa 。

(11)施工中经常检查出料弯头、输料管和管路接头,处理故障时断电、停风,发现堵管时立即停风关机。

(12)在已有混凝土面上进行喷射时,应清除剥离部分,以保证新老混凝土之间具有良好的粘结强度。

(13)新喷射的混凝土应按规定洒水养护。

(14)喷射混凝土的回弹物不得重复利用,所有的回弹混凝土应从工作面清除。

3.9 拱背回填注浆(或有空洞)

1、为保证初期支护拱背密实,初期支护完成后,在拱背压注1:1水泥沙浆,强度在3MPa 。

2、在上台阶拱部格栅拱架安装完成、喷射砼前,沿隧道纵向每环格栅钢架预埋一环注浆管,上台阶每环共三榀拱架,在每榀拱架接头附近和中间位置各预埋一条注浆管(上台阶拱脚每侧各有两根锁脚锚管,不用预埋注浆管) 。即每环预埋5根注浆管,纵向环距2.4m 。注浆管采用φ32×3.25普通水煤气管,长600mm ,露出喷射砼面350mm 。注浆管预埋位置详见“隧道开挖、支护结构断面图”,编号:1/1/SA6/G/J01/WOO/QT/02048。

3、拱背回填注浆在每环拱架锁脚锚管注浆完成及初期支护喷射砼达到设计强度后再进行,拟采取施工完成进行一次回填注浆,注浆顺序:环向先两侧、后拱顶,纵向沿隧道开挖前进方向依次注浆。

4、拱背回填注浆技术措施同超前小导管和锁脚锚管注浆技术措施。

3.10 开挖终点掌子面封闭

本区间进站段盾构掘进方向与暗挖方向相反,为保证盾构在接近暗挖段时,不致于引起隧道坍塌、抵挡盾构掘进压力,暗挖完成后掌子面进行工字钢加网喷混凝土封闭。

1、当上台阶开挖至终点时,沿开挖轮廓打设一环超前小导管并注浆,以加固前方隧道上部围岩,同时探测前方隧道的围岩情况,其布置形式、长度、外插角等与暗挖段超前小导管相同。将掌子面基本修整成垂直面。再安设最后一环格栅钢架时,同时将水平、竖直工字钢架焊接在格栅钢架上。工字钢采用I20a 。整个隧道水平方向布置3道、竖直方向布置2道。铺设钢筋网两道,然后喷C20混凝土20cm 厚封闭掌子面。详见“掌子面封闭示意图”,编号:1/1/SA6/G/J01/WOO/QT/02050。

2、下台阶开挖至掌子面后,其封闭方案与上台阶同,竖向工字钢与上台阶焊接成整体,并在连接处两侧用10厚钢板帮焊加固。竖向同时与水平工字钢焊接成整体。

3、当盾构掘进接近掌子面时,逐步减小压力、减缓掘进速度,加强对掌子面观察,必要时采取量测监控,以合理调节盾构掘进速度。

4、如探测得知前方隧道的地质条件较差,则调整掌子面封闭措施,即增加正面水平注浆加固的措施。详细内容将根据实际情况再作调整,

并在后期施工时及时提供相应程序。

3.11 混凝土导台施工

1、导台设置

砼导台施工在掌子面封闭完成后进行,从开挖终点开始,反方向进行。全长11.02m 一次浇注完毕。导台的设计尺寸:范围为隧道底部60°,导台中部厚度为150mm ,两端为120mm ,导台混凝土强度为C30。导台各部尺寸详见“混凝土盾构导台示意图”,编号:1/1/SA6/G/J01/WOO/QT/02051。

2、施工工艺顺序

①测量放线→②锚钉安设→③内外侧顶面定位钢筋安装→④钢筋网铺设→⑤砼浇灌→⑥砼捣固、导台初步成型→⑦弧面成型抹光→⑧砼养护。

3、测量放线

导台两侧顶面施工与线路曲线吻合,放线时按中线里程每5m 放出内、外侧定位点(边线及高程) 。采用两条ф22钢筋按定位点用短钢筋焊接、固定在初衬格栅钢架上,形成导台内、外侧顶面控制线,作为导台抹面控制标志。以此利用自制成形器赶平混凝土和对成形的弧面进行检查。

4、导台锚钉及钢筋网安设

放线完成后,为防止盾构推进时,导台与初衬面产生相对滑动、增加导台抗压强度及便于安设钢筋网,在喷射混凝土和导台接触面增设Φ

20、L=300mm锚钉,横向每断面3根,纵向间距600mm 。锚钉伸入喷射混凝土不小于150mm 。顶面距导台面(保护层)35mm 。采用冲击电钻钻φ

20孔,人工锤击打入喷射混凝土,通过混凝土浇注后浆液渗透达到减易植筋效果。钢筋网为φ6、200×200网孔,距导台弧形顶面(保护层)35mm ,在加工场先加工成3484×5000mm 网片,铺设时将网片按弧面点焊在锚钉上。

5、混凝土浇注

导台混凝土采用商品混凝土,浇注前一天通知商品混凝土供应商预计浇注时间、方量,正洞每延米约0.81m 3/m,洞内采用人工手推车运输、人工浇捣,每一段浇捣反方向进行,手推车运输采用在锚钉上铺木板形成运输通道。

混凝土浇捣过程中,每捣实初步成形一段,利用“自制成形器”成形弧面,然后人工抹平、抹光,再用成形器检查、抹平、抹光,如此反复,直到导台弧面达到要求为止。

6、导台与盾构切口连接处施工

为了保证盾构顺利上到导台上,在接口处的2m 长的导台坡度作微量调整,由原设计的-2.98‰改为+7‰,接口处高程降低20mm ,2m 后的导台恢复至原设计坡度和设计高程。而且导台边缘预埋840×700×10mm 钢板,加强导台边缘的强度。详见“混凝土盾构导台坡度及预埋件示意图”,编号:1/1/SA6/G/J01/WOO/QT/02052。

4. 隧道监控量测

4.1 监控量测的目的

实施监控量测的目的具体包括:

1、通过监控量测了解各施工阶段地层与支护结构的动态变化,把

握施工过程中结构所处的安全状态,判断围岩稳定性,支护可靠性。

2、用现场实测的结果弥补理论分析过程中存在的不足,并把监测结果反馈设计、指导施工。为修改施工方法、调整围岩级别、变更支护设计参数提供依据。

3、通过监控量测对工程施工可能产生的环境影响进行全面的监控。

4、通过监控量测进行隧道日常的施工管理,确保施工安全和质量。

5、通过监控量测了解该工程条件下所表现、反映出来的一些地下工程规律和特点,为今后类似工程或该工法本身的发展提供借鉴、依据和指导作用。

4.2 监控量测计划

监控量测的项目主要根据隧道工程的地质条件、围岩类别、跨度、埋深、开挖方法和支护类型等综合确定。而且,在隧道工程中进行量测,绝不是单纯地为了获取信息,而是把它作为施工管理的一个积极有效的手段,因此量测信息应能:

确切地预报破坏和变形等未来的动态,对设计参数和施工流程加以监控,以便及时掌握围岩动态而采取适当的措施(如预估最终位移值、根据监控基准调整、修改开挖和支护的顺序和时机等)。

满足作为设计变更的重要信息和各项要求,如提供设计、施工所需的重要参数(初始位移速度、作用荷载等)。

根据以上所述并结合本隧道的实际情况,拟进行A 类:洞内外观察、地表下沉、拱顶下沉等项目的施工监测项目。监测内容见下表:

监控量测项目一览表

主要监控量测项目简介如下:

1、洞内外观察

地质和支护状态观察包括工作面观察和支护结构的支护效果观察。

(1)观察频率:

每一循环进尺,都必须进行一次工作面观察,并作好客观详尽的记录。在地质变化不大地段,可每天按一个工作面记录,对已成洞地段主要是支护效果的观察,频率同工作面。

(2)观察内容:

1) 工作面工程地质和水文地质情况观察和描述:包括岩石名称,岩石产状,风化变质情况,断层、层理、节理等结构面的分布、走向、产状及频率,有无偏压或膨胀地压,工作面及毛洞自稳情况,地下水情况及影响等内容。

2) 工作面附近初期支护状态观察和已成洞的支护效果观察:包括喷

层开裂部位、宽度、长度及深度,防水效果等。

2、拱顶下沉量测

(1)量测目的:监视隧道拱顶的绝对下沉量,掌握断面的变形动态,判断支护结构的稳定性。

(2)量测方法:用全站仪进行隧道拱顶下沉量测。

沿隧道拱顶部每隔5米布设测点,2次/天,工作面开挖后及时埋测点。

3、地表下沉量测

(1)量测目的:隧道开挖时必然引起地面沉陷,量测的目的是了解: 1) 地面下沉范围,量值; 2) 地面下沉随工作面推进的规律; 3) 地面下沉稳定的时间。 (2)量测方法:

一般用精密水准仪量测,仪器精度±0.1mm 。

测点沿纵向(隧道中线方向)布置,其间距为5~6m ,并布设一个横断面,每断面布置7个测点即可。测点应在开挖形成的下沉之前埋设,一直测到下沉稳定。详细参见国贸站进站段盾构隧道施工沉降测点布置。

4.3 量测频率

1、量测频率

量测频率根据监测数据的变化情况而定,一般按下表进行。

量测频率表

2、监测数据的分析及预测

取得监测数据后,及时进行整理,绘制位移随时间或空间的变化曲线图。在取得足够数据后,还应根据散点图的数据分布情况,选择合适的函数,对监测结果进行回归,以预测该测点可能出现的最终位移值及结构的安全性,评价施工方法,确定工程措施。

3、监测数据的信息反馈

为确保监测结果质量,加快信息反馈速度,全部监测数据均有计算机管理,并绘制测点位移变化曲线图。

(1)信息反馈修正设计的基本要求

1) 现代隧道施工时,设计、施工必须紧密配合,共同研究,综合分析各项施工信息,及时进行信息反馈,最终确定和修改设计。

2) 信息反馈修正设计,系指在隧道开挖后,根据施工信息,对施工前预设计所确定的结构形式、支护参数、预留变形量、施工工艺、施工方法以及各工序施作的时间等的检验和修正,是贯穿于整个施工过程的设计阶段。

3)施工信息是指施工观察、现场地质调查、现场监控量测等得到的数据和信息。施工信息是隧道开挖后围岩稳定性的动态反映,也是修正设计的依据。对各种信息进行综合分析、互相印证,对预设计参数修正

和施工方法的改进是不可缺少的部分

(2)施工信息的应用

根据一个量测断面的施工信息综合分析处理结果,进行设计参数修正。

5. 工期安排

5.1 开挖、支护循环时间及计划指标

1、上台阶开挖、支护循环时间

上台阶开挖、支护循环时间表

每循环进尺0.7m(1榀格栅间距) 。

计划指标:每循环0.7m/17小时。计划日进尺:1m/天。

2、下台阶开挖、支护循环时间

下台阶开挖、支护循环时间表

每循环进尺0.7m(1榀格栅间距) 。

计划指标:每循环0.7m/16.5小时。计划日进尺:1.0m/天。

5.2 进度计划安排

详细工期安排见《进度计划时间表》。

6. 劳动力安排

根据本区段工程情况,抽派我公司原在深圳地铁一期工程2A 标段

购香区间右线XK9+914.792~XK10+034.792段矿山法成洞施工的全套施工、管理人员,具有相同工程的施工经验。配备劳动力详见下表:

投入劳动力表

7. 主要机械设备

主要机械设备计划表

8. 质量保证措施

1、开工前认真熟悉施工文件,计算出隧道各主要部位的标高,制定《标高表》,上报监理工程师审核后,作为施工测量的依据。

2、喷射砼前,检查开挖断面尺寸、清除杂物和松动岩体,埋设短节钢筋,以标识喷砼厚度,用高压风、高压水清洗受喷面,喷射作业分段、分片、分块、分层自下而上进行,喷射砼紧跟开挖工作面。

3、加强原材料的进货检验,把好进货关,所有材料存放及使用均标识、记录清楚,确保不合格材料不投入工程实体使用中,并且有追溯性,在施工前,需将所有有关材料特性资料提交SYSTRA 。

4、实行质量责任制,逐级落实到工班,责任到人。把工程质量和职工的奖金、评先等紧密挂钩,奖罚分明,增强工人的责任感。

5、喷砼用外加剂经试验选定质优品牌,确定最佳掺量,同时需SYSTRA 参与试验。

6、对空气湿度进行监测,当空气湿度不能满足养生要求时,必须进行喷水养护。

7、严格施工过程的质量控制

9. 施工安全保证措施 9.1 综合保证措施

1、建立以岗位责任制为中心的安全生产逐级负责制,制度明确、责任到人,奖罚分明。

2、按施工人员的比例配备足够的专职安全员,驻地管理人员一律佩证上岗,安全员佩证为红色,以示醒目。

3、在编制施工计划的同时,编制详细的安全操作规程、细则、制度及切实可行的安全技术措施,分发至工班,组织逐条落实。搞好“五同时”(即在计划、布置、检查、总结、评比生产的同时,计划、布置、检查、总结、评比安全工作) 和“三级安全教育”。

4、每一工序开始前,做出详细的施工方案和实施措施,及时做好施工技术及安全技术交底,并在施工过程中督促检查,严格坚持特殊工种持证上岗。

5、进行定期和不定期的安全检查,及时发现和解决不安全的事故隐患,杜绝违章作业和违章指挥现象,同时加大安全教育及宣传力度。

6、坚持每周一安全活动日的安全学习制度。严格执行交接班制度,坚持工前讲安全、工中检查安全、工后评比安全的“三工制”活动。

7、开工前期制定各项安全制度及防护措施: (1)各类机电设备操作规程及各项安全作业规章制度。 (2)用电安全须知及电力架设、养护作业制度。 (3)风、水管路安设及养护制度。 (4)防雷电、防洪、防火的安全专项规定。

8、针对关键工序,编制专项安全措施和专项技术交底,并设专人进行安全监督与落实,共设3名安全员负责施工安全,具体人员:毛节成,倪新龙,刘建平。

9、做好现场医护和急救工作。

9.2 施工现场安全技术措施

1、施工现场的布置符合防火、防爆、防洪、防雷电等安全规定及文明施工的要求。施工现场的生产、生活办公用房、仓库、材料堆放场、修理场应按批准的总平面布置图进行布置。

2、现场道路平整、坚实、保持畅通,危险地点悬挂安全标志,符合安全规定的标牌,施工现场设置大幅安全宣传标语。

3、现场的生产、生活区设足够的消防水源和消防设施网点,消防器有专人管理,不乱拿乱放,所有施工人员要熟悉并掌握消防设备的性能和使用方法。

4、各类房屋、库棚、料场等安全消防距离符合有关规定,现场的易燃杂物随时清理,严禁在有火种的场所或其近旁堆放易燃物品。

5、施工现场的临时用电严格按照《施工现场临时用电安全技术规范》JGJ6-88的规定执行。

6、施工中如发现危及地面建筑物或有危险品时立即停止施工,待处理完毕后方可施工。

7、从事电力、高处作业及起重作业等特殊作业人员,各种机械的操作人员及机动车辆驾驶人员,必须经过劳动部门专业培训并考试取得合格证后,方准持证独立操作。

8、施工现场设立安全标志。危险地区必须悬挂“危险”或“禁止通行”、“严禁烟火”等标志,夜间设红灯警示。


相关内容

  • 联络通道和泵房施工方案
  • 联络通道和泵房施工方案 一.联络通道及泵房位置 根据设计图纸,在区庄站-动物园站盾构区间设置一处联络通道(兼泵房),该联络通道与左线盾构隧道接口处的中心里程为ZDK12+294.343,与右线盾构隧道接口处的中心里程为YDK12+296.235. 动物园站-杨箕站盾构区间设置一处联络通道(兼泵房), ...

  • 成都地铁区间工程的施工难点及对策
  • 塑塑三堡一 成都地铁区间工程的施工难点及对策 ConstructionDifficultiesandCountermeasuresforIntervalTunnelEngineeringofChengduMetro 江新文 上海建浩工程顾问有限公司 上海200030 摘要:成都地区地质构造复杂,地下 ...

  • 路堑爆破施工作业指导书
  • 路堑爆破施工作业指导书 1.编制依据及原则 1.1编制依据 1.1.1<新建重庆至贵阳铁路(YQZQ-10标)路基施工图设计>及现场实地调查资料; 1.1.2相关施工安全管理规定及现场爆破施工经验; 1.1.3中华人民共和国国家标准GB6722-2003<爆破安全规程>: 1 ...

  • 内蒙古某铁路路基施工组织设计_secret
  • 第一章 工程概况 1.1编制说明 1.1.1编制依据 xxxxxx铁路有限责任公司的xx铁路二期(xx至xx段)线下工程施工项目招标文件. xxxx铁路二期线下工程补充文件.招标答疑文件. 铁道第一勘测设计院设计的设计图纸.设计文件.设计资料. 现场踏勘.调查所获得的有关资料. 我单位拥有的施工工法 ...

  • 土方路基填筑施工方案
  • 山东省龙口至青岛公路莱西(沈海高速)至城阳段土建工程 施工技术方案报审表 承包单位: 龙建路桥股份有限公司 合同号: 9 龙口-青岛公路莱西(沈海高速)至城阳段 土建九标段(K129+750-K140+150) 路基土石方工程 施工方案 编制: 复核: 审核: 龙建路桥股份有限公司 龙青高速公路土建 ...

  • 隧道工程监理实施细则(范本)
  • 隧道工程监理实施细则 (范 本) XXX监理咨询有限公司 二O O 九年十二月 ⅩⅩⅩⅩ 工程项目 监理实施细则 隧道工程 编制: 审核: XXXX工程监理咨询有限公司 ⅩⅩⅩ项目监理办(总监办) ⅩⅩⅩⅩ年ⅩⅩ月ⅩⅩ日 目 录 第二节 编制依据 .......................... ...

  • 涵洞台背回填施工方案_(最终版)
  • 宁都至定南(赣粤界)高速公路 安远至定南高速公路A4标 台背回填专项施工方案 编制:张景康 复核:王 栋 审核:唐为忠 中铁二十三局集团第一工程有限公司 安定高速公路A4标项目经理部 二〇一五年六月 目 录 一.工程概况 ....................................... ...

  • 挖掘作业安全管理办法
  • 管道局挖掘作业安全管理办法 第一章 总 则 第一条 为规范中国石油天然气管道局挖掘作业安全管理,控制挖掘作业风险,保证挖掘作业安全,依据中国石油天然气集团公司<挖掘作业安全管理规范>(Q/SY 1247-2009)及<管道局作业许可管理办法>等有关规定,制定本办法. 第二条 ...

  • 城市轨道(隧道)交通工程
  • 1K413010 深基坑支护及盖挖法施工 一. 内容提要 1.深基坑支护及盖挖法施工 2.盾构法施工 二.重点.难点 1.深基坑支护结构的施工要求 2.地下连续墙的施工技术 3.盖挖法施工技术 4.盾构法施工控制要求 5.盾构法施工现场的设施布置 6.应该停止盾构掘进的要求 三.内容讲解 1K413 ...