施工试验方案

目 录

1、编制依据 .............................................................. 3 2、项目概况 .............................................................. 3 3、试验委托单的填写 ...................................................... 4 3.1基本要求 ............................................................. 4 3.2委托单的填写 ......................................................... 4 4、施工现场常规试验 ...................................................... 4 4.1砼坍落度测定 ......................................................... 4 4.2砼试块制作和养护 ..................................................... 5 5.原材料和施工试验取样方法 ............................................... 5 5.1砼强度试件取样 ....................................................... 6 5.2砼抗渗试验取样及养护 ................................................. 6 5.3 钢筋原材及连接接头试验 ............................................... 7 5.3.1原材试件取样 ..................................................... 7 5.3.2钢筋接头试验取样 ................................................. 7 5.4防水卷材取样方法及数量 ............................................... 8 5.5JS防水涂料取样方法及数量 ............................................. 8 5.6 BM连锁砌块 .......................................................... 9 5.7回填土 ............................................................... 9 5.8砌筑砂浆 ............................................................ 10 5.9水泥 ................................................................ 10 5.10砂 ................................................................. 10 5.11建筑保温工程 ....................................................... 10 6、试验设备的配置及定期检验制度 ......................................... 11 6.1试验设备配置表 ...................................................... 11 6.2试验设备使用注意事项 ................................................ 11 7、试验资料 ............................................................. 11 8、试验管理制度 ......................................................... 12 8.1现场试验管理 ........................................................ 12

8.2试验人员职责 ........................................................ 12 8.3见证取样和送检制度 .................................................. 13

1、编制依据

1、《施工总承包合同》 2、施工图纸

3、《砼结构工程施工质量验收规范》 (GB50204-2015) 4、《钢筋机械连接通用技术规程》 (JGJ107-2003) 5、《钢筋焊接及验收规程》 (JGJ18-2003) 6、《建筑工程施工质量验收统一标准》 (GB50300 - 2001) 7、《屋面工程质量验收规范》 (GB50207-2002) 8、《建筑节能工程施工质量验收规范》 (GB50411-2007) 9、《砼质量控制标准》 (GB50164-2011) 10、河北省建筑工程施工质量验收技术资料管理规程

11、《建筑施工冬期施工规程》 (JGJ104-2003) 12、《地下防水工程施工质量验收规范》 (GB50208-2011) 13、《混凝土外加剂应用技术规范》 (GB50119-2003) 14、剑桥郡13期二标段施工组织设计 2、项目概况

3、试验委托单的填写 3.1基本要求

3.1.1试验资料应使用河北地方性标准规定的试验报告及相应规定的试验记录、试 验台帐。

3.1.2凡申报经审批同意的材料进场时,必须有业主、监理在场见证取样,试验合格后方可用于工程。

3.1.3如有材料试验不合格,须坚决将之退出现场,并有监理见证记录。 3.1.4送样时应分品种建立送样记录,现场简易试验应有试验记录,包括砼坍落度、试块制作记录等。 3.2委托单的填写

3.2.1字迹清晰、项目齐全、准确、真实、无未了事项,不得涂改。

3.2.2试样(件)的代表数量应填写实际进场数量,进场复验应按批验收,每组样品所代表的数量不大于规定的检验批量,超过部分应另行取样送试。

3.2.3进场日期填写材料实际进场时间,来样日期填写试件送到试验室的时间,试验日期及试验编号由试验室填写。

3.2.4对于同一强度等级的砼,原材料品种、规格、产地、厂家不变,进货批量变化,则原材料按规定取样送验,配合比报告单也应更换,以保证原材料、配合比报告单及试块报告单上原材料试验编号一致。 4、施工现场常规试验 4.1砼坍落度测定

现场测定砼坍落度,正常情况下每班2小时做1次,如发现某阶段时间坍落度不够稳定,应每搅拌车做一次,并及时做好记录。对砼坍落度不符合要求的车辆勒令退回。

砼坍落度允许偏差

4.1.1操作过程如下:

4.1.1.1塌落度筒置于平整的不吸水板上。

4.1.1.2分三层装料,每层1/3,由外向内插捣25次,并贯穿该层,顶部抹平。 4.1.1.3平稳提筒,过程不间断,在5-10s完成。 4.1.1.4测量砼的最高点与筒顶高差。 4.2砼试块制作和养护

4.2.1砼试块制作

使用振动平台振捣试块时,拌和物一次入模,振动到表面出浆不泛气泡为止,用铁抹子抹平。

4.2.2砼试块标养室

混凝土试块标养采用集装箱式标养室,标养室温度: 20±2℃ 湿度:95%以上,置放间距:10-20mm

4.2.3砼试块现场同条件养护:顶板模板拆模试块、实体检测用试块、冬施阶段的临界强度试块,同条件养护试块放于用圆12钢筋焊制的铁笼内上锁,放于现场施工试块所代表部位进行同条件养护

5.原材料和施工试验取样方法

试验报告是判定原材料、半成品、成品质量的主要技术依据之一,是工程技术资料的重要组成部分。取样是试验工作的重要一环,取样人员和见证人员应具备与工作相适应的专业知识,熟悉技术规范对取样的要求,保证试样的代表性、真实性。

5.1砼强度试件取样

5.1.1砼试样应在砼浇筑地点随机抽样而不许在泵车前,其取样方法:

1)每100m3的同配比混凝土试件取样不少于一次,每次浇筑同配比砼不足100 m3

时仍取样一次。

2)当一次连续浇筑量超过1000m3 ,同一配比的混凝土每200m3取样不得少于一次。 3)每次取样应至少留置一组标准养护试块;

4)同条件养护试件留置:竖向框架柱和剪力墙构件混凝土每层每次取样留置一组同条件养护试块,每组3个试件,用于结构实体检验。梁、板砼每段取样留置两组同条件养护试块,每组3个试件,一组同条件养护试块主要用于底模拆除时强度控制,一组

试块用于结构实体检测。

5.1.2冬期施工砼试块数量除按常规要求外,尚应至少增设三组与结构同条件养护的试块,一组用于砼同条件养护28天后转标养28天的试块,一组用于检验砼受冻前的临界强度,一组用于600℃/d。

5.1.3 用于结构实体检验的同条件养护试块留置应与监理一起选定。同条件养护试块应放在用钢筋焊接的铁笼里,并将其放置在靠近相应结构构件部位的适当位置,采取相同的养护方法进行养护。

5.1.4用于结构实体检验的同条件养护试块,应在达到等效养护龄期时进行强度试验. 等效养护龄期可取按日平均温度每日累计达到600℃.d时所对应的龄期,0℃及以下的龄期不计入,等效养护龄期不应少于14d,也不宜大于60天。 5.2砼抗渗试验取样及养护

5.2.1同一砼强度等级、同一抗渗等级、同一配合比,生产工艺基本相同的单项工程取不少于两组,每组6块;

5.2.2连续浇筑砼每500M3应留置一组抗渗试件,且每一分项工程不得少于2组; 5.2.3冬施期间应留置一组同条件养护28天后转标养28天的试块;

5.2.4试块应在浇筑地点制作,试块成型后24小时拆模,拆模后一组在标准条件下养护,一组在现场同条件养护,试块养护不少于28天,不大于90天。

5.3 钢筋原材及连接接头试验 5.3.1原材试件取样

5.3.1.1钢筋母材力学性能试验应按批进行,每批由同一厂别、同一炉罐号、同一规格、同一交货状态、同一进场时间的钢筋组成。

5.3.1.2热轧带肋钢筋、热轧光圆钢筋、低碳钢热轧园盘条每批数量不得大于60t,每批取试样一组,同一批不足60t按60t计。

5.3.1.3每组试件数量见下表:

说明:具体取样数量以固安实验室要求为准。

5.3.1.4热轧带肋和热轧光圆钢筋应从任意两根中分别切取,即在每根钢筋上切取一个用作拉伸试件,一个用作弯曲试件,低碳钢热轧圆盘条冷弯试件应取自不同盘。

5.3.1.5试件切取时,应在钢筋或盘条的任意一端截去500mm后切取,试件长度:拉伸试件≥200+10d,弯曲试件≥150+5d。

5.3.1.6 试件复检

任何检验如有某一项试验结果不符合标准要求,则从同一批中再任取双倍数量的试件进行不合格项目的复检,试验结果如出现任一个指标不合格则该批视为不合格。

5.3.1.7 钢筋原材的重量偏差

每来一批钢筋及时取样,送到有资质的检测单位进行钢筋的重量偏差检测; 5.3.2钢筋接头试验取样 滚压直螺纹连接接头取样

1)同一施工条件下采用同一批材料的同等级、同型式、同规格接头,以500个为一个验收批,不足500个按500个计。

2)对接头的每一个验收批,必须在工程结构中随机截取3个试件作为单向拉伸试

验;

3)当3个试件中有一个不合格时,应再取6个试件进行复检,复检中如仍有1个试件不合要求,则该验收批评为不合格。

4)大批量进行连接前要做班前工艺连接取样送试,试验结果合格后方可进行大批量施工。

电渣压力焊接头取样

1)同一施工条件下采用同一批材料的同等级、同型式、同规格接头,以300个为一个验收批,不足300个按300个计。

2)对接头的每一个验收批,必须在工程结构中随机截取3个试件作为单向拉伸试验;

3)当3个试件中有一个不合格时,应再取6个试件进行复检,复检中如仍有1个试件不合要求,则该验收批评为不合格。

4)大批量进行连接前要做班前工艺焊取样送试,试验结果合格后方可进行大批量施工。

5.4防水卷材取样方法及数量

5.4.1防水卷材以同一生产厂、同一品种、同一批号的产品不超过1000卷为一验收批.

5.4.2将取样的一卷卷材切除距外层卷头2500mm后,顺纵向切取长为500mm的全幅卷材试样二块,一块作物理性检验试件用,另一块备用. 5.5JS防水涂料取样方法及数量

5.5.1JS防水涂料以同一生产厂、同一品种、同一进场时间每5T为一验收批,不足5T亦为一验收批;

5.5.2每一验收批按产品的配比取样,样品总重为2KG;

5.5.3取样方法:在该批中随机抽取整桶样品,抽样的桶数见下表,应不低于表中数值。 将取样的整桶样品搅拌均匀后用取样器,在液面上、中、下三个不同部位取相同量的样品,进行再混合,搅拌均匀后,装入样品容器中,样品容器应留有约5﹪的空隙,密封并作好标志。

5.6 BM连锁砌块 5.6.1取样批的确定

以同一产地、同一规格为一验收批。具体如下:每1万块为一验收批,不足1万块按1万块计进行取样。 5.7回填土

回填土必须分层夯密实,并分层、分段取样做干密度试验。施工试验资料主要是取样的平面位置上的回填土干密度试验报告。

取样数量

1)基坑:每层100-500m2,但不少于一点。

2)挖方、填方:每100-500m2一点,但不少于一点。 3)场地平整:每400-900m2一点,但不少于一点。 4)排水沟:每层长度20-50 m2取一点,但不少于一点。

5)地(路)面基层:每层按100-500 m2㎡取一点,但不少于一点。

各层取样点应错开,并应绘制取样平面位置图,标清各层取样点位。所用土源回填前要做土壤击实试验。

5.8砌筑砂浆

5.8.1施工中取样应在使用地点的砂浆槽、砂浆运送车或搅拌机出料口,至少从三个不同部位集取,数量应多于试验用料的1-2倍。

5.8.2砌筑砂浆以同一强度等级、同一配合比、同种原材料每一楼层(基础可按一个楼层计)为一取样单位,砌体超过250M3为一取样单位,余者亦为一取样单位。

5.8.3每一取样单位标准养护试块的留置组数不得少于一组(每组六块),还应制作同条件养护试块,备用试块各一组。 试样要有代表性,每批试块(包括相对应的同条件备用试块)的试样必须取自同一次拌制的砌筑砂浆拌合物。 5.9水泥

对同一厂家、同一品种、同一标号编号的水泥为一检验批,出厂时间不超过3个月,取样数量为12KG。从20个不同部位取等量样品进行混合均匀。 5.10砂

普通混凝土用砂,按同产地、同规格分批验收。以200 M3为一批。取样数量为20-50KG,在料堆上取样时,取样部位应均匀分布。取样前先将表层铲除,然后由各部位抽取大致相等的砂共8份,组成一组样品。 5.11建筑保温工程

(1)墙体工程:保温材料、粘接材料、增强网,单位工程建筑面积在20000m2以下时各抽查不少于3组,当单位工程建筑面积在20000m2以上各抽查不少于6组。

(2)屋面工程:同一厂家、同一品种抽查不少于3组 (3)地面工程:同一厂家、同一品种抽查不少于3组 (4)现场实体检测:

1)墙体:保温板与基层的粘结强度现场拉拔试验、尼龙锚栓锚固力形成拉拔试验每个检验批不少于3组

2)底基与主体结构:承重结构混凝土回弹强度、钢筋保护层厚度、钢筋数量、位置、预埋筋抗拉强度、楼板厚度,混凝土回弹强度、数量、预埋筋抗拉强度不少于3各

构件,保护层厚度、楼板厚度不少于5个构件。

6、试验设备的配置及定期检验制度

6.1试验设备配置表

6.2试验设备使用注意事项

6.2.1立定期送检与保养试验设备台帐。

6.2.2使用试验仪器要严格按规程进行,不允许非试验人员操作。使用过程中若发现试验仪器性能不正常,应立即停用作调试或送修。

7、试验资料

7.1商品砼随车资料,收料员负责收存核验,及时把原件存放在资料室,并复印1份盖章后,由资料员报监理。

7.2材质证明资料,由材料室给试验员提供,试验员及时随进场材料作相关试验,并及时将试验资料报技术负责人,审阅合格后交资料室存档,同时复印盖章报监理。

7.3试验员及时根据进场材料和施工进度取样试验,保证先试验后施工。试验报告取回后,报技术负责人审阅合格后,送资料室备案并报监理,通知材料室对材料进行标识放行。

8、试验管理制度

8.1现场试验管理

8.1.1现场建立标准养护室(集装箱式成品标养室)。 8.1.2现场试验员应持证上岗,由技术部领导。

8.1.3试验员负责现场原材的取样和送试,砼试块的制作、养护、送试和简易土工等试验工作。

8.1.4施工期间应分层分段对试验项目按时间顺序分别连续编号,并应分品种建立台帐。

台帐包括:砼试块制作台帐 钢筋接头试验台帐

检测设备台帐 钢筋原材试验台帐 其它台帐

8.2试验人员职责

8.2.1认真贯彻国家、部及地区颁发的建筑工程的法规、规程、规定,试验方法和有关制度。

8.2.2严格按照材料检验标准有关取样的规定取样送试,对试样的代表性、真实性负责。对出具的试验报告的计算、审核及结论的正确性负责。

8.2.3一切原始数据不准随意涂改和抽撤资料,必须实事求是,字迹清楚,数据可靠,结论明确,同时应有试验、计算、审核和负责人签字,计算和审核必须有两人完成。

8.2.4对各种试验数据结果归纳总结,分别建立试验设备、试样送检等台帐。 8.2.5如有不合格试验结果,试验员及时向技术负责人报告。 8.2.6定期对试验仪器进行检验校核、保养、做好记录。

8.2.7虚心学习,不断提高专业技术水平。 8.3见证取样和送检制度

在建设单位和监理人员见证下,由试验员在现场取样,送至试验室进行试验。 8.3.1见证取样和送检项目

用于结构工程中的钢筋原材、钢筋接头、普通砼、抗渗砼、防水卷材及防水涂料。 下列项目需进行有见证取样和送检:

(一)、用于承重结构的砼试块; (二)、用于承重墙体的砌筑砂浆试块; (三)、用于承重结构的钢筋及连接接头试件 (四)、用于承重墙的砖和砼小型砌块; (五)、用于拌制砼和砌筑砂浆的水泥; (六)、用于承重结构的砼中使用的掺加剂; (七)、地下、屋面、厕浴间使用的防水材料;

(八)、国家规定必须见证取样和送检的其他试块、试件和材料。 本工程所涉及的主要试验项目 原材类:

砂、石子、水泥、外加剂、钢筋、保温材料、防水材料、砌块等。 施工及验收试验项目:

砼抗压、钢筋接头、回填土、砌筑砂浆、钢筋保护层厚度测定、砼抗渗等。 8.3.2见证取样和送检数目

8.3.2.1单位工程有见证取样和送检次数为试验总数的100%。

8.3.2.2工程的重要部位可增加见证取样和送检次数(应监理或业主要求)。 8.3.2.3送检试样在现场施工试验中随机抽检,不得另行进行。 8.3.3见证取样和送检中应注意事项:

8.3.3.1施工过程中,见证人应按照见证取样和送检计划,对施工现场的取样和送检进行见证,并在送样或其包装上作出标识。

8.3.3.2当试验不合格按有关规定允许加倍复试时,加倍取样、送检与复试亦按见证取样和送检规定实施。

8.3.3.3各种见证取样和送检试验资料必须真实、完整、符合管理规定。严禁伪造、

涂改、抽换、或丢失试验资料。

8.3.3.4每年从6月15日到9月15日为多雨季节 ,正处于主体结构施工阶段,混凝土浇筑次数较多,混凝土试块制成后应及时覆盖避免被雨淋。

8.3.3.4钢筋试件及钢筋接头试件也应该防止雨淋。

8.3.3.5标养混凝土试块应该及时放入养护室,同条件试块注意覆盖保温养护。 8.3.3.6回填土试验应该严格控制含水量,注意保温防止有冻土层出现。

9、附录

附录A 常用建筑材料进场复试项目、主要检测参数和取样依据

15

16

17

18

19

备注:本附录参看廊坊筑科检测中心相关数据,仅供参考。

20

附录B试样台账

通用试样台账

检测试验项目:

21

钢筋试样台账

钢筋连接接头试样台账

22

混凝土试件台账

23

24

25

目 录

1、编制依据 .............................................................. 3 2、项目概况 .............................................................. 3 3、试验委托单的填写 ...................................................... 4 3.1基本要求 ............................................................. 4 3.2委托单的填写 ......................................................... 4 4、施工现场常规试验 ...................................................... 4 4.1砼坍落度测定 ......................................................... 4 4.2砼试块制作和养护 ..................................................... 5 5.原材料和施工试验取样方法 ............................................... 5 5.1砼强度试件取样 ....................................................... 6 5.2砼抗渗试验取样及养护 ................................................. 6 5.3 钢筋原材及连接接头试验 ............................................... 7 5.3.1原材试件取样 ..................................................... 7 5.3.2钢筋接头试验取样 ................................................. 7 5.4防水卷材取样方法及数量 ............................................... 8 5.5JS防水涂料取样方法及数量 ............................................. 8 5.6 BM连锁砌块 .......................................................... 9 5.7回填土 ............................................................... 9 5.8砌筑砂浆 ............................................................ 10 5.9水泥 ................................................................ 10 5.10砂 ................................................................. 10 5.11建筑保温工程 ....................................................... 10 6、试验设备的配置及定期检验制度 ......................................... 11 6.1试验设备配置表 ...................................................... 11 6.2试验设备使用注意事项 ................................................ 11 7、试验资料 ............................................................. 11 8、试验管理制度 ......................................................... 12 8.1现场试验管理 ........................................................ 12

8.2试验人员职责 ........................................................ 12 8.3见证取样和送检制度 .................................................. 13

1、编制依据

1、《施工总承包合同》 2、施工图纸

3、《砼结构工程施工质量验收规范》 (GB50204-2015) 4、《钢筋机械连接通用技术规程》 (JGJ107-2003) 5、《钢筋焊接及验收规程》 (JGJ18-2003) 6、《建筑工程施工质量验收统一标准》 (GB50300 - 2001) 7、《屋面工程质量验收规范》 (GB50207-2002) 8、《建筑节能工程施工质量验收规范》 (GB50411-2007) 9、《砼质量控制标准》 (GB50164-2011) 10、河北省建筑工程施工质量验收技术资料管理规程

11、《建筑施工冬期施工规程》 (JGJ104-2003) 12、《地下防水工程施工质量验收规范》 (GB50208-2011) 13、《混凝土外加剂应用技术规范》 (GB50119-2003) 14、剑桥郡13期二标段施工组织设计 2、项目概况

3、试验委托单的填写 3.1基本要求

3.1.1试验资料应使用河北地方性标准规定的试验报告及相应规定的试验记录、试 验台帐。

3.1.2凡申报经审批同意的材料进场时,必须有业主、监理在场见证取样,试验合格后方可用于工程。

3.1.3如有材料试验不合格,须坚决将之退出现场,并有监理见证记录。 3.1.4送样时应分品种建立送样记录,现场简易试验应有试验记录,包括砼坍落度、试块制作记录等。 3.2委托单的填写

3.2.1字迹清晰、项目齐全、准确、真实、无未了事项,不得涂改。

3.2.2试样(件)的代表数量应填写实际进场数量,进场复验应按批验收,每组样品所代表的数量不大于规定的检验批量,超过部分应另行取样送试。

3.2.3进场日期填写材料实际进场时间,来样日期填写试件送到试验室的时间,试验日期及试验编号由试验室填写。

3.2.4对于同一强度等级的砼,原材料品种、规格、产地、厂家不变,进货批量变化,则原材料按规定取样送验,配合比报告单也应更换,以保证原材料、配合比报告单及试块报告单上原材料试验编号一致。 4、施工现场常规试验 4.1砼坍落度测定

现场测定砼坍落度,正常情况下每班2小时做1次,如发现某阶段时间坍落度不够稳定,应每搅拌车做一次,并及时做好记录。对砼坍落度不符合要求的车辆勒令退回。

砼坍落度允许偏差

4.1.1操作过程如下:

4.1.1.1塌落度筒置于平整的不吸水板上。

4.1.1.2分三层装料,每层1/3,由外向内插捣25次,并贯穿该层,顶部抹平。 4.1.1.3平稳提筒,过程不间断,在5-10s完成。 4.1.1.4测量砼的最高点与筒顶高差。 4.2砼试块制作和养护

4.2.1砼试块制作

使用振动平台振捣试块时,拌和物一次入模,振动到表面出浆不泛气泡为止,用铁抹子抹平。

4.2.2砼试块标养室

混凝土试块标养采用集装箱式标养室,标养室温度: 20±2℃ 湿度:95%以上,置放间距:10-20mm

4.2.3砼试块现场同条件养护:顶板模板拆模试块、实体检测用试块、冬施阶段的临界强度试块,同条件养护试块放于用圆12钢筋焊制的铁笼内上锁,放于现场施工试块所代表部位进行同条件养护

5.原材料和施工试验取样方法

试验报告是判定原材料、半成品、成品质量的主要技术依据之一,是工程技术资料的重要组成部分。取样是试验工作的重要一环,取样人员和见证人员应具备与工作相适应的专业知识,熟悉技术规范对取样的要求,保证试样的代表性、真实性。

5.1砼强度试件取样

5.1.1砼试样应在砼浇筑地点随机抽样而不许在泵车前,其取样方法:

1)每100m3的同配比混凝土试件取样不少于一次,每次浇筑同配比砼不足100 m3

时仍取样一次。

2)当一次连续浇筑量超过1000m3 ,同一配比的混凝土每200m3取样不得少于一次。 3)每次取样应至少留置一组标准养护试块;

4)同条件养护试件留置:竖向框架柱和剪力墙构件混凝土每层每次取样留置一组同条件养护试块,每组3个试件,用于结构实体检验。梁、板砼每段取样留置两组同条件养护试块,每组3个试件,一组同条件养护试块主要用于底模拆除时强度控制,一组

试块用于结构实体检测。

5.1.2冬期施工砼试块数量除按常规要求外,尚应至少增设三组与结构同条件养护的试块,一组用于砼同条件养护28天后转标养28天的试块,一组用于检验砼受冻前的临界强度,一组用于600℃/d。

5.1.3 用于结构实体检验的同条件养护试块留置应与监理一起选定。同条件养护试块应放在用钢筋焊接的铁笼里,并将其放置在靠近相应结构构件部位的适当位置,采取相同的养护方法进行养护。

5.1.4用于结构实体检验的同条件养护试块,应在达到等效养护龄期时进行强度试验. 等效养护龄期可取按日平均温度每日累计达到600℃.d时所对应的龄期,0℃及以下的龄期不计入,等效养护龄期不应少于14d,也不宜大于60天。 5.2砼抗渗试验取样及养护

5.2.1同一砼强度等级、同一抗渗等级、同一配合比,生产工艺基本相同的单项工程取不少于两组,每组6块;

5.2.2连续浇筑砼每500M3应留置一组抗渗试件,且每一分项工程不得少于2组; 5.2.3冬施期间应留置一组同条件养护28天后转标养28天的试块;

5.2.4试块应在浇筑地点制作,试块成型后24小时拆模,拆模后一组在标准条件下养护,一组在现场同条件养护,试块养护不少于28天,不大于90天。

5.3 钢筋原材及连接接头试验 5.3.1原材试件取样

5.3.1.1钢筋母材力学性能试验应按批进行,每批由同一厂别、同一炉罐号、同一规格、同一交货状态、同一进场时间的钢筋组成。

5.3.1.2热轧带肋钢筋、热轧光圆钢筋、低碳钢热轧园盘条每批数量不得大于60t,每批取试样一组,同一批不足60t按60t计。

5.3.1.3每组试件数量见下表:

说明:具体取样数量以固安实验室要求为准。

5.3.1.4热轧带肋和热轧光圆钢筋应从任意两根中分别切取,即在每根钢筋上切取一个用作拉伸试件,一个用作弯曲试件,低碳钢热轧圆盘条冷弯试件应取自不同盘。

5.3.1.5试件切取时,应在钢筋或盘条的任意一端截去500mm后切取,试件长度:拉伸试件≥200+10d,弯曲试件≥150+5d。

5.3.1.6 试件复检

任何检验如有某一项试验结果不符合标准要求,则从同一批中再任取双倍数量的试件进行不合格项目的复检,试验结果如出现任一个指标不合格则该批视为不合格。

5.3.1.7 钢筋原材的重量偏差

每来一批钢筋及时取样,送到有资质的检测单位进行钢筋的重量偏差检测; 5.3.2钢筋接头试验取样 滚压直螺纹连接接头取样

1)同一施工条件下采用同一批材料的同等级、同型式、同规格接头,以500个为一个验收批,不足500个按500个计。

2)对接头的每一个验收批,必须在工程结构中随机截取3个试件作为单向拉伸试

验;

3)当3个试件中有一个不合格时,应再取6个试件进行复检,复检中如仍有1个试件不合要求,则该验收批评为不合格。

4)大批量进行连接前要做班前工艺连接取样送试,试验结果合格后方可进行大批量施工。

电渣压力焊接头取样

1)同一施工条件下采用同一批材料的同等级、同型式、同规格接头,以300个为一个验收批,不足300个按300个计。

2)对接头的每一个验收批,必须在工程结构中随机截取3个试件作为单向拉伸试验;

3)当3个试件中有一个不合格时,应再取6个试件进行复检,复检中如仍有1个试件不合要求,则该验收批评为不合格。

4)大批量进行连接前要做班前工艺焊取样送试,试验结果合格后方可进行大批量施工。

5.4防水卷材取样方法及数量

5.4.1防水卷材以同一生产厂、同一品种、同一批号的产品不超过1000卷为一验收批.

5.4.2将取样的一卷卷材切除距外层卷头2500mm后,顺纵向切取长为500mm的全幅卷材试样二块,一块作物理性检验试件用,另一块备用. 5.5JS防水涂料取样方法及数量

5.5.1JS防水涂料以同一生产厂、同一品种、同一进场时间每5T为一验收批,不足5T亦为一验收批;

5.5.2每一验收批按产品的配比取样,样品总重为2KG;

5.5.3取样方法:在该批中随机抽取整桶样品,抽样的桶数见下表,应不低于表中数值。 将取样的整桶样品搅拌均匀后用取样器,在液面上、中、下三个不同部位取相同量的样品,进行再混合,搅拌均匀后,装入样品容器中,样品容器应留有约5﹪的空隙,密封并作好标志。

5.6 BM连锁砌块 5.6.1取样批的确定

以同一产地、同一规格为一验收批。具体如下:每1万块为一验收批,不足1万块按1万块计进行取样。 5.7回填土

回填土必须分层夯密实,并分层、分段取样做干密度试验。施工试验资料主要是取样的平面位置上的回填土干密度试验报告。

取样数量

1)基坑:每层100-500m2,但不少于一点。

2)挖方、填方:每100-500m2一点,但不少于一点。 3)场地平整:每400-900m2一点,但不少于一点。 4)排水沟:每层长度20-50 m2取一点,但不少于一点。

5)地(路)面基层:每层按100-500 m2㎡取一点,但不少于一点。

各层取样点应错开,并应绘制取样平面位置图,标清各层取样点位。所用土源回填前要做土壤击实试验。

5.8砌筑砂浆

5.8.1施工中取样应在使用地点的砂浆槽、砂浆运送车或搅拌机出料口,至少从三个不同部位集取,数量应多于试验用料的1-2倍。

5.8.2砌筑砂浆以同一强度等级、同一配合比、同种原材料每一楼层(基础可按一个楼层计)为一取样单位,砌体超过250M3为一取样单位,余者亦为一取样单位。

5.8.3每一取样单位标准养护试块的留置组数不得少于一组(每组六块),还应制作同条件养护试块,备用试块各一组。 试样要有代表性,每批试块(包括相对应的同条件备用试块)的试样必须取自同一次拌制的砌筑砂浆拌合物。 5.9水泥

对同一厂家、同一品种、同一标号编号的水泥为一检验批,出厂时间不超过3个月,取样数量为12KG。从20个不同部位取等量样品进行混合均匀。 5.10砂

普通混凝土用砂,按同产地、同规格分批验收。以200 M3为一批。取样数量为20-50KG,在料堆上取样时,取样部位应均匀分布。取样前先将表层铲除,然后由各部位抽取大致相等的砂共8份,组成一组样品。 5.11建筑保温工程

(1)墙体工程:保温材料、粘接材料、增强网,单位工程建筑面积在20000m2以下时各抽查不少于3组,当单位工程建筑面积在20000m2以上各抽查不少于6组。

(2)屋面工程:同一厂家、同一品种抽查不少于3组 (3)地面工程:同一厂家、同一品种抽查不少于3组 (4)现场实体检测:

1)墙体:保温板与基层的粘结强度现场拉拔试验、尼龙锚栓锚固力形成拉拔试验每个检验批不少于3组

2)底基与主体结构:承重结构混凝土回弹强度、钢筋保护层厚度、钢筋数量、位置、预埋筋抗拉强度、楼板厚度,混凝土回弹强度、数量、预埋筋抗拉强度不少于3各

构件,保护层厚度、楼板厚度不少于5个构件。

6、试验设备的配置及定期检验制度

6.1试验设备配置表

6.2试验设备使用注意事项

6.2.1立定期送检与保养试验设备台帐。

6.2.2使用试验仪器要严格按规程进行,不允许非试验人员操作。使用过程中若发现试验仪器性能不正常,应立即停用作调试或送修。

7、试验资料

7.1商品砼随车资料,收料员负责收存核验,及时把原件存放在资料室,并复印1份盖章后,由资料员报监理。

7.2材质证明资料,由材料室给试验员提供,试验员及时随进场材料作相关试验,并及时将试验资料报技术负责人,审阅合格后交资料室存档,同时复印盖章报监理。

7.3试验员及时根据进场材料和施工进度取样试验,保证先试验后施工。试验报告取回后,报技术负责人审阅合格后,送资料室备案并报监理,通知材料室对材料进行标识放行。

8、试验管理制度

8.1现场试验管理

8.1.1现场建立标准养护室(集装箱式成品标养室)。 8.1.2现场试验员应持证上岗,由技术部领导。

8.1.3试验员负责现场原材的取样和送试,砼试块的制作、养护、送试和简易土工等试验工作。

8.1.4施工期间应分层分段对试验项目按时间顺序分别连续编号,并应分品种建立台帐。

台帐包括:砼试块制作台帐 钢筋接头试验台帐

检测设备台帐 钢筋原材试验台帐 其它台帐

8.2试验人员职责

8.2.1认真贯彻国家、部及地区颁发的建筑工程的法规、规程、规定,试验方法和有关制度。

8.2.2严格按照材料检验标准有关取样的规定取样送试,对试样的代表性、真实性负责。对出具的试验报告的计算、审核及结论的正确性负责。

8.2.3一切原始数据不准随意涂改和抽撤资料,必须实事求是,字迹清楚,数据可靠,结论明确,同时应有试验、计算、审核和负责人签字,计算和审核必须有两人完成。

8.2.4对各种试验数据结果归纳总结,分别建立试验设备、试样送检等台帐。 8.2.5如有不合格试验结果,试验员及时向技术负责人报告。 8.2.6定期对试验仪器进行检验校核、保养、做好记录。

8.2.7虚心学习,不断提高专业技术水平。 8.3见证取样和送检制度

在建设单位和监理人员见证下,由试验员在现场取样,送至试验室进行试验。 8.3.1见证取样和送检项目

用于结构工程中的钢筋原材、钢筋接头、普通砼、抗渗砼、防水卷材及防水涂料。 下列项目需进行有见证取样和送检:

(一)、用于承重结构的砼试块; (二)、用于承重墙体的砌筑砂浆试块; (三)、用于承重结构的钢筋及连接接头试件 (四)、用于承重墙的砖和砼小型砌块; (五)、用于拌制砼和砌筑砂浆的水泥; (六)、用于承重结构的砼中使用的掺加剂; (七)、地下、屋面、厕浴间使用的防水材料;

(八)、国家规定必须见证取样和送检的其他试块、试件和材料。 本工程所涉及的主要试验项目 原材类:

砂、石子、水泥、外加剂、钢筋、保温材料、防水材料、砌块等。 施工及验收试验项目:

砼抗压、钢筋接头、回填土、砌筑砂浆、钢筋保护层厚度测定、砼抗渗等。 8.3.2见证取样和送检数目

8.3.2.1单位工程有见证取样和送检次数为试验总数的100%。

8.3.2.2工程的重要部位可增加见证取样和送检次数(应监理或业主要求)。 8.3.2.3送检试样在现场施工试验中随机抽检,不得另行进行。 8.3.3见证取样和送检中应注意事项:

8.3.3.1施工过程中,见证人应按照见证取样和送检计划,对施工现场的取样和送检进行见证,并在送样或其包装上作出标识。

8.3.3.2当试验不合格按有关规定允许加倍复试时,加倍取样、送检与复试亦按见证取样和送检规定实施。

8.3.3.3各种见证取样和送检试验资料必须真实、完整、符合管理规定。严禁伪造、

涂改、抽换、或丢失试验资料。

8.3.3.4每年从6月15日到9月15日为多雨季节 ,正处于主体结构施工阶段,混凝土浇筑次数较多,混凝土试块制成后应及时覆盖避免被雨淋。

8.3.3.4钢筋试件及钢筋接头试件也应该防止雨淋。

8.3.3.5标养混凝土试块应该及时放入养护室,同条件试块注意覆盖保温养护。 8.3.3.6回填土试验应该严格控制含水量,注意保温防止有冻土层出现。

9、附录

附录A 常用建筑材料进场复试项目、主要检测参数和取样依据

15

16

17

18

19

备注:本附录参看廊坊筑科检测中心相关数据,仅供参考。

20

附录B试样台账

通用试样台账

检测试验项目:

21

钢筋试样台账

钢筋连接接头试样台账

22

混凝土试件台账

23

24

25


相关内容

  • 项目技术管理
  • 九.项目技术管理 1.项目技术管理内容 技术管理工作内容 施工技术准备施工过程技术管理技术总结 .图纸会审 2.施工组织设计编制1.施工方案编制2.施工技术交底 3.安全技术总交底 4.施工预检 5.施工隐检 6.钢筋.构件加工单 7.工程洽商 8.施工试验管理 9.施工测量管理 10.施工计量管理 ...

  • 路基冲击碾压工艺性试验施工方案
  • 新 建 连 徐 铁 路 工 程 路基冲击碾压施工方案 中铁十二局集团有限公司 连徐铁路工程指挥部 二0一七年七月 新 建 连 徐 铁 路 工 程 路基冲击碾压施工方案 编制: 复核: 审核: 中铁十二局集团有限公司 连徐铁路工程指挥部 二0一七年七月 目 录 一. 编制依据 ............ ...

  • 土石混填路基试验段施工技术方案
  • 江口县至转塘复线工程 路基二工区 (K4+840~隧道进口) 路基工程 土石混填试验段施工方案 编制: 审核: 批准: 江口至转塘复线二工区 2013年3月1日 目 录 一.编制依据及工程概况 1. 编制依据 2. 设计标准 3. 工程概况 二.试验段的选择.目的及意义 1. 试验段的选择 2. 试 ...

  • 勘察技术方案
  • 1 综合说明 本勘察方案,系根据业主提供的"某工程地质勘察工程"岩土工程勘察招标文件及总平面图,对建筑条件和岩土工程条件进行分析并预测后制订的. 2 勘察方案 本勘察方案编制是根据拟建建筑物性质.设计对该工程提出的岩土工程勘察技术要求和我们对本工程已知岩土工程条件的分析,针对要解 ...

  • 建设工程勘察设计大纲(暗标投标文件)
  • 建设工程勘察设计大纲(暗标投标文件) 一.勘察设计工作内容.工作方案及进度计划 1.1 勘察设计工作内容 按招标文件要求及本项目特点,工程勘测主要内容为:查明.分析.评价建设场地的地质地理环境特征.岩土工程条件.地下管线埋设情况.溶(土)洞发育情况.软弱地基范围及深度.土石比鉴定.地形图测量和补测等 ...

  • 强夯试验段施工方案
  • 延安新区一期综合开发工程 淤积土地基强夯处理试验段 施 工 方 案 榆林市长盛集团路桥工程建设有限公司 二0一二年五月五日 淤积土地基处理强夯试验段施工方案 一.工程概况 延安新区建设是延安市平山造地.上山建城,拓展城市发展空间,实施"中疏外扩"城市发展战略的重大举措. 延安新区 ...

  • 2015二建机电知识点(案例)
  • 2015年二建<机电> 1.钢材的类型及应用 P3 2.电力电缆类型及应用 P93.泵.风机.压缩机的性能参数 P10-114.起重吊装方案的管理P27(1)吊装方案的编制与审批 ①属于危险性较大的分部分项工程范围的吊装工程,施工单位应编制专项方案,技术部门组织本施工单位技术.安全.质量 ...

  • 土建工程师手册
  • 工程部土建工程师工作流程 (以框架结构施工流程为例) 注:红色字体需你充实的内容 土建工程师现场工作流程 一.工程师进场 1工器具领用 2劳保用品领用 3提交相关证件,办理相关证件 二.施工技术准备工作 1从资料室领取施工图纸(建筑图纸.施工图.及相关资料) 2阅读施工图纸 (1)提出图纸问题 (2 ...

  • 换热器水压试验通用工工艺
  • Q B 中国石化集团 企业(通用工艺) 标准 第四建设公司 ★静设备工程★ 序列号××× 换热器水压试验通用施工工艺 2006-××-×× 发布 2006-××-×× 实施 中国石化集团第四建设公司技术处 发布 换热器水压试验通用施工工艺 1 适用范围 1.1 本工艺适用于石油化工装置换热器水压试验 ...

  • 审批意见用语:
  • "经审核承包单位开工前准备工作已完成,满足开工条件.同意于××年××月××日开工". 审批意见用语: a)同意 "经复查停工令所提问题已处理完毕,满足工程质量(工艺流程)要求条件.同意于××年××月××日复工". 1.项目管理实施规划(施工组织设计)应由施工承 ...